4540 1/2 E YELLOWSTONE ST 90032

Certificate Information: 4540 1/2 E YELLOWSTONE ST 90032

Application / Permit
23014-10000-00950
Plan Check / Job No.
B23LA04361
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan - convert (e) garage to (n) 1-story ADU with addition per LAMC 12.22 A.33 (c)(d) R3 occupancy
Permit Issued
Issued on 12/26/2023
Issuing Office
Current Status
Issued on 12/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/15/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 KELVIN CHUONG
Corrections Issued 4/7/2023 KELVIN CHUONG
Quality Review Completed 4/12/2023 RODOLFO ARIAS
Applicant returned to address corrections 11/8/2023 KELVIN CHUONG
Applicant returned to address corrections 12/6/2023 KELVIN CHUONG
Plan Check Approved 12/15/2023 KELVIN CHUONG
Issued 12/26/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/27/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 6/27/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/14/2023 WALLIE JONG
Sewer availability Cleared 7/14/2023 WALLIE JONG
"D" conditions Cleared 10/3/2023 MATHEW QUAN
"Q" conditions Cleared 10/3/2023 MATHEW QUAN
Construction near power lines Cleared 10/10/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/1/2023 KELVIN CHUONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/10/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/17/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 7/26/2024 Approved BRENDAN MORELLI
HVAC-Rough 7/26/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 7/26/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 7/31/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Approved LILIANA PORTILLO
HVAC-Rough 7/31/2024 Approved LILIANA PORTILLO
Insulation 8/6/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 8/6/2024 Partial Approval LILIANA PORTILLO
Drywall Nailing 8/9/2024 Approved LILIANA PORTILLO
Green Building Rough 8/9/2024 Approved LILIANA PORTILLO
Insulation 8/9/2024 Approved LILIANA PORTILLO
Shower Pan 8/9/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/14/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/30/2024 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 12/30/2024 Corrections Issued NICHOLAS LOPEZ
Final 12/30/2024 Corrections Issued NICHOLAS LOPEZ
Green Building Final 12/30/2024 Approved NICHOLAS LOPEZ
HVAC-Final 12/30/2024 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 12/30/2024 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 12/30/2024 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 1/10/2025 Corrections Issued LILIANA PORTILLO
Final 1/10/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 1/10/2025 Approved LILIANA PORTILLO
PLUMBING-Final 1/10/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Approved LILIANA PORTILLO