4010 W 59TH ST 90043
Certificate Information: 4010 W 59TH ST 90043
- Application / Permit
- 23014-10000-00917
- Plan Check / Job No.
- B22LA26980
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan- Conversion of existing 1-story garage and storage with addition to 2-story ADU and storage per ordinance with exterior deck
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2023 | MINA HABILI |
| Corrections Issued | 3/16/2023 | MINA HABILI |
| Applicant returned to address corrections | 12/1/2023 | DANIEL YIP |
| Applicant returned to address corrections | 12/20/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/27/2024 | DANIEL SANJUAN |
| Applicant returned to address corrections | 4/19/2024 | ADAM HEGAZI |
| Applicant returned to address corrections | 4/30/2024 | ADAM HEGAZI |
| Plan Check Approved | 5/7/2024 | MINA HABILI |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 7/21/2025 | MICHAEL LEWIS |
| Permit Finaled | 7/21/2025 | DEROLD HAUFF |
| CofO Issued | 7/21/2025 | DEROLD HAUFF |
| Permit Finaled | 7/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2023 | NEIL TUANO |
| Miscellaneous | Cleared | 6/27/2023 | NEIL TUANO |
| Roof/Waste drainage to street | Cleared | 6/27/2023 | NEIL TUANO |
| Sewer availability | Cleared | 6/27/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | NEIL TUANO |
| Low Impact Development (LID) | Cleared | 11/28/2023 | SAMUEL LINN |
| Grading Pre-Inspection | Cleared | 12/2/2023 | MINA HABILI |
| Construction near power lines | Cleared | 3/19/2024 | TINA MIRANDA |
Contact Information
| Contractor | Creative Remodeling #1 Inc; Lic. No.: 1014676-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/29/2024 | Approved | JOSE MACIAS |
| Underground Mechanical | 8/29/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 9/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/30/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 9/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 9/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 10/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 10/21/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/12/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/12/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 11/12/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 11/12/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 11/18/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/21/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 11/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 11/21/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 11/21/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/27/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 12/11/2024 | Corrections Issued | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 12/11/2024 | No Access for Inspection | AMIR NAZARIAN |
| Green Building Rough | 12/11/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 12/11/2024 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 12/17/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 12/17/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 12/17/2024 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 12/23/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | AMIR NAZARIAN |
| Green Building Rough | 1/6/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 1/6/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 1/6/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 1/6/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 1/24/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 4/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 4/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 4/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 4/8/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Special/Order Compliance | 4/15/2025 | Corrections Issued | WAYNE REGESTER |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | WAYNE REGESTER |
| Final | 4/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 4/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Smoke Detectors | 4/18/2025 | Approved | WAYNE REGESTER |
| Final | 4/28/2025 | Partial Approval | WAYNE REGESTER |
| Green Building Final | 4/28/2025 | Approved | WAYNE REGESTER |
| Pre-Inspection | 4/30/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 5/5/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/15/2025 | Approved | WAYNE REGESTER |
| Final | 7/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 7/21/2025 | OK to Issue CofO | MICHAEL LEWIS |