1730 N REEDVALE LANE 90049
Certificate Information: 1730 N REEDVALE LANE 90049
- Application / Permit
- 23014-10000-00885
- Plan Check / Job No.
- B23LA04017
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Remodel entire (E) SFD with attached garage and ground floor addition to front entry and rear of building.
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Current Status
- Issued on 8/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | HELEN NGUYEN |
| Corrections Issued | 3/17/2023 | HELEN NGUYEN |
| Quality Review Completed | 3/17/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/21/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/28/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/7/2023 | HELEN NGUYEN |
| Plan Check Approved | 7/14/2023 | HELEN NGUYEN |
| Issued | 8/9/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/14/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/14/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/14/2023 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/14/2023 | DINAH GARIN |
| Sewer availability | Cleared | 4/14/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2023 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/5/2023 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 6/21/2023 | HELEN NGUYEN |
| BHO/Hillside ordinance | Cleared | 6/28/2023 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2023 | Partial Inspection | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 9/21/2023 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/26/2023 | Conditional Approval | ARAM AVEDISIAN |
| Wood Frame | 10/25/2023 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 10/30/2023 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 11/7/2023 | Partial Approval | KEVIN SARGSYAN |
| Gas Test | 11/30/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/30/2023 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 12/8/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/8/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/12/2023 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 2/13/2024 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 2/14/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 2/14/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 3/15/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/28/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 3/28/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 4/15/2024 | Approved | KENNETH NAGLE |
| Drywall Nailing | 4/19/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 5/22/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/29/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/26/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 9/26/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/26/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/30/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 9/30/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 9/30/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 10/1/2024 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/1/2024 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 10/1/2024 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/2/2024 | Approved | KEVIN SARGSYAN |
| Final | 10/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 10/2/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 10/2/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/9/2024 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 10/11/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/11/2024 | Approved | KEVIN SARGSYAN |