4327 E HATFIELD PL 90032
Certificate Information: 4327 E HATFIELD PL 90032
- Application / Permit
- 23014-10000-00876
- Plan Check / Job No.
- B23LA03963
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST FLOOR AND 2ND FLOOR ADDITION ADU TO EXISTING GARAGE. 1ST FLOOR ADDITION TO BE 437 SF. 2ND FLOR ADDITION TO BE 738 SF.
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 3/22/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/23/2023 | KEN GILL |
| Plan Check Approved | 9/6/2023 | CRYSTEL MAALOUF |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 11/19/2024 | LILIANA PORTILLO |
| Permit Finaled | 11/26/2024 | DEROLD HAUFF |
| CofO Issued | 11/26/2024 | DEROLD HAUFF |
| Permit Finaled | 11/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2023 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | DAVID VO |
| Sewer availability | Cleared | 4/27/2023 | DAVID VO |
| Construction near power lines | Cleared | 8/4/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 8/28/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/28/2023 | JEANIE LAM |
| GPI Written Notices | Cleared | 9/6/2023 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 9/6/2023 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Reyes Edy; Lic. No.: 990315-B | 4333 MULTNOMAH STREET LOS ANGELES, CA 90032 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/2/2024 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 4/2/2024 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 5/8/2024 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/8/2024 | Corrections Issued | LILIANA PORTILLO |
| Grounding or Bonding | 5/8/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/13/2024 | Partial Approval | LILIANA PORTILLO |
| Grounding or Bonding | 5/13/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/24/2024 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 6/25/2024 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 7/2/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 8/9/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/9/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 8/9/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/26/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/29/2024 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/29/2024 | Approved | LILIANA PORTILLO |
| Insulation | 9/6/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/6/2024 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 9/12/2024 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 9/12/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/12/2024 | Approved | ANTHONY RAMOS |
| Special/Order Compliance | 9/12/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| ELECTRICAL-Final | 11/13/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 11/13/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/15/2024 | Approved | LILIANA PORTILLO |
| Final | 11/15/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 11/15/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/15/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/15/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/15/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 11/15/2024 | Approved | LILIANA PORTILLO |