4327 E HATFIELD PL 90032

Certificate Information: 4327 E HATFIELD PL 90032

Application / Permit
23014-10000-00876
Plan Check / Job No.
B23LA03963
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST FLOOR AND 2ND FLOOR ADDITION ADU TO EXISTING GARAGE. 1ST FLOOR ADDITION TO BE 437 SF. 2ND FLOR ADDITION TO BE 738 SF.
Permit Issued
Issued on 9/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 CRYSTEL MAALOUF
Corrections Issued 3/22/2023 CRYSTEL MAALOUF
Quality Review Completed 3/23/2023 KEN GILL
Plan Check Approved 9/6/2023 CRYSTEL MAALOUF
Issued 9/8/2023 APPLICANT
CofO in Progress 11/19/2024 LILIANA PORTILLO
Permit Finaled 11/26/2024 DEROLD HAUFF
CofO Issued 11/26/2024 DEROLD HAUFF
Permit Finaled 11/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/27/2023 DAVID VO
Eng Process Fee Ord 176,300 Cleared 4/27/2023 DAVID VO
Sewer availability Cleared 4/27/2023 DAVID VO
Construction near power lines Cleared 8/4/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 8/28/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/28/2023 JEANIE LAM
GPI Written Notices Cleared 9/6/2023 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 9/6/2023 CRYSTEL MAALOUF

Contact Information

Contractor Reyes Edy; Lic. No.: 990315-B 4333 MULTNOMAH STREET      LOS ANGELES, CA 90032
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/2/2024 Approved BRENDAN MORELLI
Underground Mechanical 4/2/2024 Partial Approval BRENDAN MORELLI
Deputy Drilled-In Anchors 5/8/2024 Approved LILIANA PORTILLO
Footing/Foundation/Slab 5/8/2024 Corrections Issued LILIANA PORTILLO
Grounding or Bonding 5/8/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 5/13/2024 Partial Approval LILIANA PORTILLO
Grounding or Bonding 5/13/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 6/24/2024 Approved LILIANA PORTILLO
Deputy Wood Construction 6/25/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval LILIANA PORTILLO
Underground Mechanical 7/2/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval LILIANA PORTILLO
HVAC-Rough 8/9/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 8/9/2024 Approved LILIANA PORTILLO
Shower Pan 8/9/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 8/26/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 8/29/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Approved LILIANA PORTILLO
HVAC-Rough 8/29/2024 Approved LILIANA PORTILLO
Insulation 9/6/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 9/6/2024 Partial Approval LILIANA PORTILLO
Drywall Nailing 9/12/2024 Corrections Issued ANTHONY RAMOS
Insulation 9/12/2024 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/12/2024 Approved ANTHONY RAMOS
Special/Order Compliance 9/12/2024 Not Ready for Inspection ANTHONY RAMOS
ELECTRICAL-Final 11/13/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 11/13/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/15/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/15/2024 Approved LILIANA PORTILLO
Final 11/15/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 11/15/2024 Approved LILIANA PORTILLO
Green Building Rough 11/15/2024 Approved LILIANA PORTILLO
HVAC-Final 11/15/2024 Approved LILIANA PORTILLO
PLUMBING-Final 11/15/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 11/15/2024 Approved LILIANA PORTILLO