14336 W HATTERAS ST 91401
Certificate Information: 14336 W HATTERAS ST 91401
- Application / Permit
- 23014-10000-00868
- Plan Check / Job No.
- B23LA03922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED ACCESSORY DWELLING UNIT WITH PORCH ADDITION TO (E) DETACHED GARAGE TO COMPLY WITH 12.22 A.33(c) AND (d) (1-STORY)
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2023 | MADISON ODELL |
| Corrections Issued | 5/10/2023 | MADISON ODELL |
| Applicant returned to address corrections | 8/29/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 9/13/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 9/21/2023 | CARLOS MONTES |
| Issued | 10/11/2023 | APPLICANT |
| CofO in Progress | 5/22/2024 | RYAN SALAZAR |
| CofO in Progress | 6/10/2024 | ROBERT GOLD |
| No Progress | 6/10/2024 | ROBERT GOLD |
| CofO in Progress | 10/31/2024 | RYAN SALAZAR |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
| CofO Issued | 11/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hold | Cleared | 5/15/2023 | MARIA VENDIVIL |
| Address approval | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/1/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/21/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/21/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 9/20/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/20/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/26/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 11/2/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/14/2023 | Partial Approval | RYAN SALAZAR |
| Sewer | 12/1/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/27/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 12/27/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/27/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 12/27/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 12/29/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/3/2024 | Approved | RYAN SALAZAR |
| Insulation | 1/3/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/8/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/8/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | RYAN SALAZAR |
| Final | 5/15/2024 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 5/15/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/15/2024 | Approved | RYAN SALAZAR |
| Final | 5/21/2024 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 5/21/2024 | Approved | RYAN SALAZAR |
| Final | 6/26/2024 | Corrections Issued | RYAN SALAZAR |
| Final | 11/1/2024 | OK to Issue CofO | RYAN SALAZAR |