14953 W GREENLEAF ST 91403
Certificate Information: 14953 W GREENLEAF ST 91403
- Application / Permit
- 23014-10000-00858
- Plan Check / Job No.
- B23LA03835
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan REMODEL ENTIRE OF (E) SFD, AND ADDTION AT REAR, NEW DECK
- Permit Issued
- Issued on 2/29/2024
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2023 | KHUONG TRUONG |
| Corrections Issued | 3/12/2023 | KHUONG TRUONG |
| Plan Check Approved | 2/6/2024 | KHUONG TRUONG |
| Issued | 2/29/2024 | APPLICANT |
| CofO in Progress | 4/9/2026 | JAVIER RAMOS JR |
| Permit Finaled | 4/16/2026 | RUBEN SALAS |
| CofO Issued | 4/16/2026 | RUBEN SALAS |
| Permit Finaled | 4/16/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/23/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 3/28/2023 | KIRK LINKLATER |
| Low Impact Development (LID) | Cleared | 1/5/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/9/2024 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/5/2024 | Conditional Approval | DAVID MATSON |
| Pre-Inspection | 2/11/2025 | Corrections Issued | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 4/9/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/10/2025 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 4/10/2025 | Approved | JAVIER RAMOS JR |
| Wood Frame | 4/25/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/18/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/18/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 6/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 6/18/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 6/18/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 6/26/2025 | Approved | JACK KARGODORIAN |
| Insulation | 7/3/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 7/3/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 7/25/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 7/25/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 2/13/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 2/13/2026 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 2/13/2026 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/13/2026 | Approved | JACK KARGODORIAN |
| HVAC-Final | 2/13/2026 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 2/13/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 2/13/2026 | Approved | JACK KARGODORIAN |
| Final | 2/26/2026 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/8/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/8/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| PLUMBING-Final | 4/8/2026 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/8/2026 | Approved | JAVIER RAMOS JR |