8817 N ENFIELD AVE 91325
Certificate Information: 8817 N ENFIELD AVE 91325
- Application / Permit
- 23014-10000-00854
- Plan Check / Job No.
- B23LA03822
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage into ADU and addition to converted ADU per LAMC 12.22 A.33 (c)-(d). All work per engineer. SEE COMMENTS.
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Valley
- Current Status
- Issued on 8/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | VICTOR CHEN |
| Corrections Issued | 3/14/2023 | VICTOR CHEN |
| Building Plans Picked Up | 3/15/2023 | APPLICANT |
| Applicant returned to address corrections | 7/18/2023 | DANIEL SMILEY |
| Plan Check Approved | 7/20/2023 | DANIEL SANJUAN |
| Issued | 8/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/20/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 4/10/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 4/11/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 6/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/10/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 8/18/2023 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/22/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/7/2023 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/7/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/20/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/20/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/20/2023 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 10/3/2023 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 10/3/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 10/3/2023 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 10/3/2023 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/3/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/3/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/6/2023 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/13/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 10/13/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 10/13/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 10/13/2023 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 10/13/2023 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 10/24/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 11/13/2023 | Approved | MICHEL ABAJAN |
| Gas Test | 11/22/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 11/22/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 11/22/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 12/6/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/6/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 12/6/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 12/6/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/31/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 12/31/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 12/31/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/31/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | JAVIER RAMOS JR |