6600 W 82ND ST 90045

Certificate Information: 6600 W 82ND ST 90045

Application / Permit
23014-10000-00839
Plan Check / Job No.
B23LA01000
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Eplan GROUND FLOOR ADDITION GARAGE TO (E) 1-STORY GARAGE AND REC. ROOM.
Permit Issued
Issued on 10/3/2023
Issuing Office
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 MAHNAZ NOURHASHEMI
Corrections Issued 3/2/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 3/14/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/19/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 9/28/2023 MAHNAZ NOURHASHEMI
Issued 10/3/2023 APPLICANT
CofO in Progress 4/14/2026 JESUS PINEDA
Permit Finaled 4/21/2026 RICHARD STEINBACH
CofO Issued 4/21/2026 RICHARD STEINBACH
Permit Finaled 4/21/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2023 JASON NG
Permit Cleared 4/18/2023 JASON NG
Specific Plan Cleared 4/19/2023 JIMMY VIVAR
Low Impact Development (LID) Cleared 7/11/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/13/2023 JASON NG
Trees in Parkway Cleared 7/24/2023 ADALBERTO VERA
Miscellaneous Cleared 9/11/2023 ALBERT TAM

Contact Information

Contractor Golden Age Construction Inc; Lic. No.: 1040171-B 8265 SUNSET BLVD UNIT 205      WEST HOLLYWOOD, CA 90046
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/31/2023 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 11/1/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 11/28/2023 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 11/28/2023 Approved BOBBY KEY
Green Building Rough 11/28/2023 Not Ready for Inspection BOBBY KEY
Deputy Steel/Welding 11/30/2023 Conditional Approval BOBBY KEY
Deputy Steel/Welding 1/18/2024 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 1/31/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Conditional Approval BOBBY KEY
Deputy Wood Construction 2/13/2024 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 5/2/2024 Corrections Issued BOBBY KEY
Green Building Rough 5/2/2024 Not Ready for Inspection BOBBY KEY
Rough-Elec/Plmb/HVAC 5/2/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 5/17/2024 Approved BOBBY KEY
Green Building Rough 5/17/2024 Approved BOBBY KEY
Interior/Exterior Lathing 5/17/2024 Partial Approval BOBBY KEY
Drywall Nailing 7/23/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 2/18/2025 Corrections Issued TEMISTOCLES CAAL
Green Building Final 2/18/2025 Approved TEMISTOCLES CAAL
HVAC-Final 2/18/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 2/18/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Not Ready TEMISTOCLES CAAL
Smoke Detectors 2/18/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 4/21/2025 Approved JESUS PINEDA
Final 4/21/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Not Required JESUS PINEDA
Final 4/13/2026 OK to Issue CofO JESUS PINEDA