3333 W BERKELEY AVE 90026
Certificate Information: 3333 W BERKELEY AVE 90026
- Application / Permit
- 23014-10000-00836
- Plan Check / Job No.
- B23LA03737
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) gargae to ADU with 1st and 2md story addition per ordinance.
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/7/2023 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 3/11/2023 | GARO TELMI |
| Building Plans Picked Up | 3/16/2023 | APPLICANT |
| Plan Check Approved | 4/20/2023 | FARSHAD ALIMOHAMADI |
| Issued | 4/20/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
| CofO Issued | 10/28/2024 | RUBEN SALAS |
| Permit Finaled | 10/28/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 3/17/2023 | TREVOR QUAN |
| Tenant Habitability Plan | Cleared | 3/21/2023 | MICHAEL SOTO |
| Low Impact Development (LID) | Cleared | 4/14/2023 | TOMMY YIN |
| Address approval | Cleared | 4/17/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 4/18/2023 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 4/20/2023 | FARSHAD ALIMOHAMADI |
Contact Information
| Contractor | Castillo Construction Services Inc; Lic. No.: 1076756-B | 5617 LEXINGTON AVE APT 1 LOS ANGELES, CA 91106 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/2/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/6/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/23/2023 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 9/11/2023 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 9/11/2023 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/13/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 9/15/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 9/15/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 9/15/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 9/19/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 9/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Final | 12/1/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/1/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 12/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 5/1/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 5/1/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 5/1/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/13/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/13/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/13/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 10/21/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 10/21/2024 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/21/2024 | Approved | HAMIK HARTOUNIAN |