305 S AVENUE 56 90042
Certificate Information: 305 S AVENUE 56 90042
- Application / Permit
- 23014-10000-00817
- Plan Check / Job No.
- B23LA03657
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two story addition to rear of an (E) SFD.
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | HELEN NGUYEN |
| Corrections Issued | 3/16/2023 | HELEN NGUYEN |
| Quality Review Completed | 3/23/2023 | KEN GILL |
| Building Plans Picked Up | 3/24/2023 | APPLICANT |
| Applicant returned to address corrections | 4/6/2023 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/13/2023 | HELEN NGUYEN |
| Plan Check Approved | 5/18/2023 | HELEN NGUYEN |
| Issued | 5/18/2023 | APPLICANT |
| CofO in Progress | 3/12/2024 | LILIANA PORTILLO |
| CofO Issued | 3/19/2024 | DEROLD HAUFF |
| Permit Finaled | 3/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/14/2023 | HELEN NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/4/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 5/12/2023 | HELEN NGUYEN |
Contact Information
| Architect | Lennon,, Grace Elizabeth; Lic. No.: C35479 | 305 S AVE 56 LOS ANGELES, CA 90042 |
| Contractor | Owner-Builder | , |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/9/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | AMY COLIN |
| Insulation | 6/28/2023 | Partial Approval | AMY COLIN |
| Wood Frame | 7/11/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 10/24/2023 | Approved | AMY COLIN |
| Green Building Rough | 10/24/2023 | Approved | AMY COLIN |
| HVAC-Rough | 10/24/2023 | Approved | AMY COLIN |
| MERV13>=Rough | 10/24/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 10/24/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 10/27/2023 | Partial Approval | AMY COLIN |
| Insulation | 10/27/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/27/2023 | Partial Approval | AMY COLIN |
| Shower Pan | 10/27/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | AMY COLIN |
| Drywall Nailing | 11/3/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 11/3/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 2/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/15/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/15/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 2/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 2/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Final | 2/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 2/15/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 2/15/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 2/26/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 2/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Final | 2/26/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/26/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/4/2024 | Corrections Issued | BRENDAN MORELLI |
| Final | 3/4/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Final | 3/4/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 3/11/2024 | Approved | LILIANA PORTILLO |
| Final | 3/11/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 3/11/2024 | Approved | LILIANA PORTILLO |