3604 S 5TH AVE 90018

Certificate Information: 3604 S 5TH AVE 90018

Application / Permit
23014-10000-00807
Plan Check / Job No.
B23LA03618
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN- (N) 18'x20' and 5'10"x 5' ADDITIONS TO (E) SFD, INTERIOR REMODEL TO ADD 1 BEDROOM/2 BATH/LIVING ROOM, REFRAMING FOR PORTION OF (E) SFD. WORK PER ENGINEERING.
Permit Issued
Issued on 4/3/2023
Issuing Office
Current Status
CofO Issued on 3/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2023 APPLICANT
Assigned to Plan Check Engineer 3/8/2023 ISIS ARGUETA
Corrections Issued 3/9/2023 ISIS ARGUETA
Applicant returned to address corrections 3/23/2023 ISIS ARGUETA
Plan Check Approved 3/30/2023 DANIEL YIP
Issued 4/3/2023 APPLICANT
CofO in Progress 3/6/2024 JUSTIN HAWLEY
CofO Issued 3/12/2024 DEROLD HAUFF
Permit Finaled 3/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/18/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/21/2023 CINDY QI
HPOZ Cleared 3/21/2023 MAX LODER
Sewer availability Cleared 3/23/2023 CINDY QI

Contact Information

Contractor New Era Builder Inc; Lic. No.: 1101778-B       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2023 Corrections Issued CALEB MEISTER
Deputy Drilled-In Anchors 4/12/2023 Conditional Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 4/17/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 4/17/2023 Conditional Approval MICHAEL LEWIS
Deputy Wood Construction 5/19/2023 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 5/26/2023 Partial Approval CALEB MEISTER
ELECTRICAL-Rough 5/26/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Approved CALEB MEISTER
HVAC-Rough 5/26/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 5/26/2023 Corrections Issued CALEB MEISTER
Rough-Elec/Plmb/HVAC 5/26/2023 Partial Inspection CALEB MEISTER
Wood Frame 5/26/2023 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 3/1/2024 Approved JUSTIN HAWLEY
Final 3/1/2024 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 3/1/2024 Approved JUSTIN HAWLEY
Green Building Final 3/1/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 3/1/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 3/5/2024 Approved JUSTIN HAWLEY
Final 3/5/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 3/5/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 3/5/2024 Approved JUSTIN HAWLEY