3604 S 5TH AVE 90018
Certificate Information: 3604 S 5TH AVE 90018
- Application / Permit
- 23014-10000-00807
- Plan Check / Job No.
- B23LA03618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- (N) 18'x20' and 5'10"x 5' ADDITIONS TO (E) SFD, INTERIOR REMODEL TO ADD 1 BEDROOM/2 BATH/LIVING ROOM, REFRAMING FOR PORTION OF (E) SFD. WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Current Status
- CofO Issued on 3/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2023 | ISIS ARGUETA |
| Corrections Issued | 3/9/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 3/23/2023 | ISIS ARGUETA |
| Plan Check Approved | 3/30/2023 | DANIEL YIP |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 3/6/2024 | JUSTIN HAWLEY |
| CofO Issued | 3/12/2024 | DEROLD HAUFF |
| Permit Finaled | 3/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/18/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2023 | CINDY QI |
| HPOZ | Cleared | 3/21/2023 | MAX LODER |
| Sewer availability | Cleared | 3/23/2023 | CINDY QI |
Contact Information
| Contractor | New Era Builder Inc; Lic. No.: 1101778-B | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2023 | Corrections Issued | CALEB MEISTER |
| Deputy Drilled-In Anchors | 4/12/2023 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/17/2023 | Conditional Approval | MICHAEL LEWIS |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/26/2023 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 5/26/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 5/26/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 5/26/2023 | Corrections Issued | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 5/26/2023 | Partial Inspection | CALEB MEISTER |
| Wood Frame | 5/26/2023 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/1/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/1/2024 | Approved | JUSTIN HAWLEY |
| Green Building Final | 3/1/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 3/1/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/5/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/5/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 3/5/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/5/2024 | Approved | JUSTIN HAWLEY |