210 1/2 W AMABEL ST 90065

Certificate Information: 210 1/2 W AMABEL ST 90065

Application / Permit
23014-10000-00797
Plan Check / Job No.
B23LA03576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING 1-STORY ACCESSORY STRUCTURE CONVERSION TO ADU WITH PROPOSED 2-STORY ADDITION PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 ERIC WONG
Corrections Issued 3/11/2023 ERIC WONG
Quality Review Completed 3/14/2023 PETER KIM
Building Plans Picked Up 3/17/2023 APPLICANT
Applicant returned to address corrections 6/16/2023 CARLOS MONTES
Plan Check Approved 7/14/2023 CARLOS MONTES
Issued 7/31/2023 APPLICANT
CofO in Progress 5/10/2024 OSVALDO PARAMO
Permit Finaled 5/15/2024 DEROLD HAUFF
CofO Issued 5/15/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/22/2023 JEANIE LAM
Roof/Waste drainage to street Cleared 3/22/2023 JEANIE LAM
Grading Pre-Inspection Cleared 4/26/2023 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 5/23/2023 JEANIE LAM
Sewer availability Cleared 5/23/2023 JEANIE LAM
Supp. Use District POD/CDO/TDO Cleared 6/22/2023 NICOLE SANCHEZ
ZI Cleared 6/22/2023 NICOLE SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/10/2023 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 10/19/2023 Conditional Approval OSVALDO PARAMO
PLUMBING-Rough 10/19/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 12/7/2023 Partial Approval AMY COLIN
Green Building Rough 12/7/2023 Not Ready for Inspection AMY COLIN
MERV13>=Rough 12/7/2023 Approved AMY COLIN
Deputy Wood Construction 12/12/2023 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 12/20/2023 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 12/20/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved OSVALDO PARAMO
HVAC-Rough 12/20/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 12/20/2023 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 12/22/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/22/2023 Approved OSVALDO PARAMO
Green Building Rough 12/22/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/22/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 12/22/2023 Approved OSVALDO PARAMO
Insulation 12/28/2023 Approved AMY COLIN
Drywall Nailing 1/10/2024 Approved OSVALDO PARAMO
Shower Pan 1/23/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/24/2024 Approved OSVALDO PARAMO
Underground Mechanical 3/6/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 3/29/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 4/25/2024 Approved OSVALDO PARAMO
PLUMBING-Final 4/25/2024 Approved OSVALDO PARAMO
Final 5/6/2024 OK to Issue CofO OSVALDO PARAMO
Footing/Foundation/Slab 5/6/2024 Approved OSVALDO PARAMO
Green Building Final 5/6/2024 Approved OSVALDO PARAMO
MERV13>=Final 5/6/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 5/6/2024 Approved OSVALDO PARAMO
Smoke Detectors 5/6/2024 Approved OSVALDO PARAMO