210 1/2 W AMABEL ST 90065
Certificate Information: 210 1/2 W AMABEL ST 90065
- Application / Permit
- 23014-10000-00797
- Plan Check / Job No.
- B23LA03576
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING 1-STORY ACCESSORY STRUCTURE CONVERSION TO ADU WITH PROPOSED 2-STORY ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 7/31/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | ERIC WONG |
| Corrections Issued | 3/11/2023 | ERIC WONG |
| Quality Review Completed | 3/14/2023 | PETER KIM |
| Building Plans Picked Up | 3/17/2023 | APPLICANT |
| Applicant returned to address corrections | 6/16/2023 | CARLOS MONTES |
| Plan Check Approved | 7/14/2023 | CARLOS MONTES |
| Issued | 7/31/2023 | APPLICANT |
| CofO in Progress | 5/10/2024 | OSVALDO PARAMO |
| Permit Finaled | 5/15/2024 | DEROLD HAUFF |
| CofO Issued | 5/15/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/22/2023 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/26/2023 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | JEANIE LAM |
| Sewer availability | Cleared | 5/23/2023 | JEANIE LAM |
| Supp. Use District POD/CDO/TDO | Cleared | 6/22/2023 | NICOLE SANCHEZ |
| ZI | Cleared | 6/22/2023 | NICOLE SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/10/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/19/2023 | Conditional Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 10/19/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 12/7/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 12/7/2023 | Not Ready for Inspection | AMY COLIN |
| MERV13>=Rough | 12/7/2023 | Approved | AMY COLIN |
| Deputy Wood Construction | 12/12/2023 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/20/2023 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 12/20/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 12/20/2023 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/22/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/22/2023 | Approved | OSVALDO PARAMO |
| Green Building Rough | 12/22/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/22/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 12/22/2023 | Approved | OSVALDO PARAMO |
| Insulation | 12/28/2023 | Approved | AMY COLIN |
| Drywall Nailing | 1/10/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 1/23/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/24/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 3/6/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/29/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/25/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 4/25/2024 | Approved | OSVALDO PARAMO |
| Final | 5/6/2024 | OK to Issue CofO | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/6/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 5/6/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 5/6/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 5/6/2024 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/6/2024 | Approved | OSVALDO PARAMO |