8870 W HARGIS ST 90034
Certificate Information: 8870 W HARGIS ST 90034
- Application / Permit
- 23014-10000-00784
- Plan Check / Job No.
- B23LA03491
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan MASTER BEDROOM ADDITION AT REAR OF (E) 1-STORY SFD WITH KITECHEN REMODEL AND WINDOW CHANGE
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2023 | JOSEPH RAFOLS |
| Corrections Issued | 3/13/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 4/7/2023 | MINA HABILI |
| Plan Check Approved | 4/14/2023 | MINA HABILI |
| Issued | 4/17/2023 | APPLICANT |
| CofO in Progress | 10/16/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
| CofO Issued | 10/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/14/2023 | CINDY QI |
| Sewer availability | Cleared | 3/14/2023 | CINDY QI |
| Specific Plan | Cleared | 3/14/2023 | KYLE WINSTON |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2023 | CINDY QI |
| Miscellaneous | Cleared | 4/14/2023 | DANIEL SCHNEIDEREIT |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2023 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 5/30/2023 | Corrections Issued | JEREMY TODD |
| Footing/Foundation/Slab | 6/6/2023 | Approved | JEREMY TODD |
| Deputy Drilled-In Anchors | 6/7/2023 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/20/2023 | Partial Approval | JEREMY TODD |
| PLUMBING-Rough | 6/20/2023 | Partial Approval | JEREMY TODD |
| Insulation | 6/22/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 6/22/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 7/5/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 7/5/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| MERV13>=Rough | 7/5/2023 | Approved | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/5/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/7/2023 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 7/7/2023 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/7/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 7/10/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 7/17/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/11/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Rough | 8/11/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 8/11/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/11/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 8/15/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 8/16/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/22/2023 | Approved | MEL KHACHATOURIAN |
| Final | 9/22/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 9/22/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 9/22/2023 | Approved | MEL KHACHATOURIAN |
| MERV13>=Final | 9/22/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 9/22/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 10/2/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 10/2/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 10/2/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 10/2/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 10/6/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| MERV13>=Final | 10/6/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 10/6/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 10/12/2023 | Corrections Issued | MEL KHACHATOURIAN |
| MERV13>=Final | 10/12/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 10/12/2023 | Approved | MEL KHACHATOURIAN |
| Final | 10/17/2023 | OK to Issue CofO | MEL KHACHATOURIAN |