9314 1/2 S HOOVER ST 90044

Certificate Information: 9314 1/2 S HOOVER ST 90044

Application / Permit
23014-10000-00767
Plan Check / Job No.
B23LA03449
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (e) garage into ADU and add s.f. per LAMC 12.22 A.33 (c)(d) Total = 788.00 s.f.
Permit Issued
Issued on 3/31/2023
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 KHUONG TRUONG
Corrections Issued 3/6/2023 KHUONG TRUONG
Plan Check Approved 3/30/2023 KHUONG TRUONG
Issued 3/31/2023 APPLICANT
CofO in Progress 9/24/2024 BEN MOLSTAD
Permit Finaled 10/1/2024 DEROLD HAUFF
CofO Issued 10/1/2024 DEROLD HAUFF
Permit Finaled 10/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/22/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 3/22/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/29/2023 CELINA MORENO
Sewer availability Cleared 3/29/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/27/2023 Partial Approval JAMES CHAVEZ
Deputy Drilled-In Anchors 8/17/2023 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 8/18/2023 No Access for Inspection JAMES CHAVEZ
Footing/Foundation/Slab 8/23/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 8/28/2023 Partial Inspection JAMES CHAVEZ
Footing/Foundation/Slab 9/1/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Not Ready for Inspection JAMES CHAVEZ
Gas Test 11/29/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 11/29/2023 Corrections Issued JAMES CHAVEZ
Underground Mechanical 11/29/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Approved JOHN KLARIN
Green Building Rough 12/5/2023 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 12/5/2023 Corrections Issued JOHN KLARIN
Underground Mechanical 12/5/2023 Approved JOHN KLARIN
Insulation 1/17/2024 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 1/17/2024 Partial Approval JAMES CHAVEZ
Shower Pan 1/17/2024 Approved JAMES CHAVEZ
Insulation 1/23/2024 Approved JAMES CHAVEZ
Drywall Nailing 2/6/2024 No Access for Inspection JAMES CHAVEZ
Drywall Nailing 2/15/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 2/15/2024 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 7/24/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 7/24/2024 Corrections Issued BEN MOLSTAD
Final 7/24/2024 Corrections Issued BEN MOLSTAD
Green Building Final 7/24/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 7/24/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Final 7/24/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 7/24/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 7/24/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 8/27/2024 Approved JOSEPH MCGARRY
Final 8/27/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 8/27/2024 Approved JOSEPH MCGARRY
HVAC-Final 8/27/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 8/27/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 8/27/2024 Not Required JOSEPH MCGARRY
Final 9/11/2024 No Access for Inspection BEN MOLSTAD
Final 9/24/2024 OK to Issue CofO BEN MOLSTAD