1072 1/2 S WEST BLVD 90019

Certificate Information: 1072 1/2 S WEST BLVD 90019

Application / Permit
23014-10000-00757
Plan Check / Job No.
B23LA03380
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** (N) Accessory Dwelling Unit attached to (E) Detached garage at raer of the lot PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/23/2023
Issuing Office
Current Status
CofO Issued on 2/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2023 APPLICANT
Assigned to Plan Check Engineer 3/3/2023 ALFREDO JARA
Corrections Issued 3/4/2023 ALFREDO JARA
Applicant returned to address corrections 5/30/2023 EDWIN ESPIN
Plan Check Approved 6/20/2023 EDWIN ESPIN
Issued 6/23/2023 APPLICANT
CofO in Progress 2/7/2024 JUSTIN HAWLEY
No Progress 2/8/2024 DEROLD HAUFF
CofO in Progress 2/8/2024 DEROLD HAUFF
Permit Finaled 2/8/2024 DEROLD HAUFF
CofO Issued 2/8/2024 DEROLD HAUFF
Permit Finaled 2/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/18/2023 CINDY QI
Tenant Habitability Plan Cleared 4/13/2023 ISMAEL HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 4/17/2023 CINDY QI
Sewer availability Cleared 4/17/2023 CINDY QI
Low Impact Development (LID) Cleared 5/16/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/22/2023 TREVOR QUAN
Construction near power lines Cleared 6/9/2023 RIDWAN HARDY
Construction within easement Cleared 6/9/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770
Engineer Wu,, Harold Ping-Hung; Lic. No.: NA35693       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 8/16/2023 Approved CALEB MEISTER
Underground Mechanical 8/16/2023 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 8/18/2023 Corrections Issued CALEB MEISTER
Footing/Foundation/Slab 8/18/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Barrier 8/18/2023 Approved CALEB MEISTER
Excavation/Setback/Form/Re-Bar 8/29/2023 Approved CALEB MEISTER
Footing/Foundation/Slab 8/29/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved CALEB MEISTER
Wood Frame 9/25/2023 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 10/2/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 10/2/2023 Approved CALEB MEISTER
HVAC-Rough 10/2/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 10/2/2023 Approved CALEB MEISTER
METHANE-Rough 10/2/2023 Approved CALEB MEISTER
PLUMBING-Rough 10/2/2023 Approved CALEB MEISTER
Shower Pan 10/2/2023 Approved CALEB MEISTER
Insulation 10/5/2023 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 10/5/2023 Approved CALEB MEISTER
Drywall Nailing 10/12/2023 Approved CALEB MEISTER
Insulation 10/12/2023 Approved CALEB MEISTER
Drywall Nailing 10/13/2023 Approved CALEB MEISTER
Service/Power Release 11/16/2023 Not Ready for Inspection CALEB MEISTER
Underground Mechanical 11/27/2023 Approved JUSTIN HAWLEY
ELECTRICAL-Final 12/7/2023 Approved JUSTIN HAWLEY
Final 12/7/2023 Corrections Issued JUSTIN HAWLEY
HVAC-Final 12/7/2023 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Final 12/7/2023 Not Ready for Inspection JUSTIN HAWLEY
Final 1/26/2024 Corrections Issued JUSTIN HAWLEY
HVAC-Final 1/26/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 1/26/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV No Gas JUSTIN HAWLEY
Smoke Detectors 1/26/2024 Approved JUSTIN HAWLEY
Final 2/7/2024 OK to Issue CofO JUSTIN HAWLEY
Service/Power Release 2/7/2024 Approved JUSTIN HAWLEY