125 E PARK PL 1-2 90291
Certificate Information: 125 E PARK PL 1-2 90291
- Application / Permit
- 23014-10000-00737
- Plan Check / Job No.
- B23LA03284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL AND ADDITION TO (E) TWO STORY DUPLEX TO CONVERT INTO A THREE STORY DUPLEX W/ ATTACHED TWO CAR GARAGE PER DIR-2023-4555-CDP-SPPC-ADJ
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Current Status
- Issued on 10/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 3/30/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 4/4/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/26/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 1/3/2024 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 1/7/2025 | DANIEL YIP |
| Applicant returned to address corrections | 3/11/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/18/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/23/2025 | SERGIO GUTIERREZ |
| No Progress | 4/23/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/23/2025 | SERGIO GUTIERREZ |
| Issued | 4/23/2025 | APPLICANT |
| Refund in Progress | 9/23/2025 | SELENIA GARCIA |
| Refund Closed | 10/22/2025 | EMMA PANGILINAN |
| Issued | 10/22/2025 | EMMA PANGILINAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/4/2023 | NATHAN ROMINE |
| Miscellaneous | Cleared | 4/4/2023 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 4/22/2023 | KURT CORRAL |
| Address approval | Cleared | 6/13/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2023 | AHMED AMARRAGY |
| Highway dedication | Cleared | 6/13/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 6/13/2023 | AHMED AMARRAGY |
| Low Impact Development (LID) | Cleared | 8/29/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/28/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 3/10/2025 | ASHLEY RODARTE |
| ZI | Cleared | 3/10/2025 | ASHLEY RODARTE |
| Coastal Zone | Cleared | 3/14/2025 | ASHLEY RODARTE |
| Specific Plan | Cleared | 3/14/2025 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 3/17/2025 | ASHLEY RODARTE |
| Specific Plan | Cleared | 3/17/2025 | ASHLEY RODARTE |
| Specific Plan | Cleared | 4/2/2025 | HAMID GHAEMMAGHAMI |
Contact Information
| Contractor | Ofir Construction Inc; Lic. No.: 1036242-B | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2025 | Partial Inspection | FARHAD DADBIN |
| Pre-Inspection | 7/21/2025 | Corrections Issued | FARHAD DADBIN |
| Footing/Foundation/Slab | 9/4/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/4/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/12/2025 | Partial Approval | JESUS RODRIGUEZ |