8609 N TAMPA AVE 91324

Certificate Information: 8609 N TAMPA AVE 91324

Application / Permit
23014-10000-00732
Plan Check / Job No.
B23LA03264
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO NEW ADU WITH ADDITION PER LAMC 12.22 A.33 (c)(d) ALL WORK DONE PER WFPP
Permit Issued
Issued on 12/7/2023
Issuing Office
Metro
Current Status
CofO in Progress on 8/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 KHUONG TRUONG
Corrections Issued 3/8/2023 KHUONG TRUONG
Applicant returned to address corrections 5/24/2023 JOSEPH RAFOLS
Applicant returned to address corrections 9/15/2023 MINA HABILI
Applicant returned to address corrections 10/13/2023 VICTOR CHEN
Plan Check Approved 12/1/2023 LUKE GONZALES
Issued 12/7/2023 APPLICANT
CofO in Progress 10/3/2024 CHRIS CHRISTENSEN
No Progress 8/28/2025 HENRY KIM
CofO in Progress 8/28/2025 HENRY KIM

Permit Application Clearance Information

Address approval Cleared 7/5/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 7/5/2023 CHRISTINA BRACO
Sewer availability Cleared 7/5/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 8/17/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/12/2024 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/12/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/12/2024 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/14/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 3/22/2024 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/7/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 Partial Approval JEFFREY HARTLINE
HVAC-Rough 6/7/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 6/7/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 6/14/2024 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/14/2024 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 6/14/2024 Partial Approval CHRIS CHRISTENSEN
Insulation 6/24/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Partial Approval ARUTYUN MADATYAN
Insulation 7/5/2024 Approved ARUTYUN MADATYAN
Shower Pan 7/5/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 7/9/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 7/17/2024 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 8/26/2024 Approved CHRIS CHRISTENSEN
Final 8/26/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 8/26/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 8/26/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 8/26/2024 Approved CHRIS CHRISTENSEN
Final 9/25/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 9/25/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/25/2024 SGSOV Approved CHRIS CHRISTENSEN
Final 10/2/2024 OK to Issue CofO CHRIS CHRISTENSEN
Service/Power Release 10/2/2024 Approved CHRIS CHRISTENSEN