1509 W 87TH ST 90047
Certificate Information: 1509 W 87TH ST 90047
- Application / Permit
- 23014-10000-00729
- Plan Check / Job No.
- B23LA03258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-2" x 18'-1" DETACHED GARAGE AND 18'-2" x 10'-8" CARPORT WITH ADDITION OF 38'-0" x 14'-10" TO (N) DETACHED ACCESSORY DWELLING UNIT(1006 S.F) PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/6/2023
- Issuing Office
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/3/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 6/6/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/14/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 7/3/2023 | MIROOSH KHACHATOORIAN |
| Issued | 7/6/2023 | APPLICANT |
| CofO in Progress | 10/17/2025 | MICHAEL LEWIS |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 3/16/2023 | STEVE MELGAR |
| Low Impact Development (LID) | Cleared | 5/26/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/4/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/14/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 2/14/2025 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 2/20/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2025 | Approved | JOSE MACIAS |
| Pre-Inspection | 3/4/2025 | Approved | JOSE MACIAS |
| Special/Order Compliance | 3/19/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 3/20/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 3/20/2025 | Approved | JOSE MACIAS |
| Sewer | 3/20/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/3/2025 | Partial Approval | WAYNE REGESTER |
| Interior/Exterior Lathing | 4/3/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 4/9/2025 | Approved | JOSE MACIAS |
| Insulation | 4/15/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 4/29/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/29/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 4/29/2025 | Approved | ANTHONY RAMOS |
| Final | 6/24/2025 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 7/9/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Gas Test | 7/9/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 7/9/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 7/9/2025 | Approved | WAYNE REGESTER |
| Service/Power Release | 7/9/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 9/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 9/18/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 10/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 10/2/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 10/16/2025 | OK to Issue CofO | MICHAEL LEWIS |
| Smoke Detectors | 10/16/2025 | Approved | MICHAEL LEWIS |