806 1/2 N VISTA ST 90046

Certificate Information: 806 1/2 N VISTA ST 90046

Application / Permit
23014-10000-00728
Plan Check / Job No.
B23LA03257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 14'-2.5" x 7'-1" ADDITION TO AND CONVERT THE 19'-11" x 17'-10.5" (E) DETACHED GARAGE TO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP.
Permit Issued
Issued on 10/3/2023
Issuing Office
Current Status
Issued on 10/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/27/2023 APPLICANT
Assigned to Plan Check Engineer 3/3/2023 SARKIS HARABEDIAN
Corrections Issued 3/4/2023 SARKIS HARABEDIAN
Plan Check Approved 9/22/2023 SARKIS HARABEDIAN
Issued 10/3/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/16/2023 CINDY QI
Roof/Waste drainage to street Cleared 3/16/2023 CINDY QI
Construction near power lines Cleared 8/10/2023 RIDWAN HARDY
Construction within easement Cleared 8/10/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/24/2023 CINDY QI
Sewer availability Cleared 8/24/2023 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/16/2023 Partial Inspection LILIANA PORTILLO
Pre-Inspection 10/18/2023 Approved RUBEN PEREZ
Excavation/Setback/Form/Re-Bar 11/27/2023 Not Ready for Inspection ROBERT NILES
Footing/Foundation/Slab 11/27/2023 Not Ready for Inspection ROBERT NILES
METHANE-Barrier 11/27/2023 Not Ready for Inspection ROBERT NILES
METHANE-Subgrade 11/27/2023 Not Ready for Inspection ROBERT NILES
Excavation/Setback/Form/Re-Bar 12/5/2023 Approved ROBERT NILES
Footing/Foundation/Slab 12/5/2023 Approved ROBERT NILES
METHANE-Barrier 12/5/2023 Approved ROBERT NILES
METHANE-Subgrade 12/5/2023 Approved ROBERT NILES
Wood Frame 2/7/2024 Not Ready for Inspection RUBEN PEREZ
PLUMBING-Rough 8/25/2025 Not Ready for Inspection PETER RUBIO
Pre-Inspection 8/25/2025 Approved PETER RUBIO
Wood Frame 8/25/2025 Not Ready for Inspection PETER RUBIO
Wood Frame 9/8/2025 Not Ready for Inspection PETER RUBIO
ELECTRICAL-Rough 12/9/2025 Not Ready for Inspection PETER RUBIO
PLUMBING-Rough 12/9/2025 Not Ready for Inspection PETER RUBIO
Pre-Inspection 12/9/2025 Approved PETER RUBIO
ELECTRICAL-Rough 5/14/2026 Approved PETER RUBIO
PLUMBING-Rough 5/14/2026 Approved PETER RUBIO
Wood Frame 5/14/2026 Corrections Issued PETER RUBIO