3465 1/2 W LARGA AVE 90039
Certificate Information: 3465 1/2 W LARGA AVE 90039
- Application / Permit
- 23014-10000-00715
- Plan Check / Job No.
- B23LA03212
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 14' X 18' GARAGE AND (N) IRREGULARLY SHAPED 15'10" X 14'2" ADDITION TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 11/9/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | MADISON ODELL |
| Corrections Issued | 3/3/2023 | MADISON ODELL |
| Plan Check Approved | 10/10/2023 | MADISON ODELL |
| Issued | 11/9/2023 | APPLICANT |
| CofO in Progress | 7/29/2024 | THOMAS LOGRASSO |
| CofO Issued | 8/5/2024 | DEROLD HAUFF |
| Permit Finaled | 8/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/12/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/12/2023 | RIDWAN HARDY |
| Address approval | Cleared | 6/27/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/27/2023 | WALLIE JONG |
| Sewer availability | Cleared | 6/27/2023 | WALLIE JONG |
| ZI | Cleared | 6/29/2023 | NATHAN ROMINE |
Contact Information
| Contractor | Bless It Construction Inc; Lic. No.: 1048746-B | , |
| Engineer | Tiongco,, John Lazarraga; Lic. No.: NA70915 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/1/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 12/4/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/7/2023 | No Access for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/14/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/12/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/12/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/12/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/26/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/31/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 2/2/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/6/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 2/6/2024 | Partial Approval | JOSH MEISTER |
| Drywall Nailing | 2/8/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 4/26/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/26/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 5/8/2024 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 5/17/2024 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 7/29/2024 | OK to Issue CofO | THOMAS LOGRASSO |