3122 W MADERA AVE 90039
Certificate Information: 3122 W MADERA AVE 90039
- Application / Permit
- 23014-10000-00714
- Plan Check / Job No.
- B23LA03208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Existing Garage conversion to ADU WITH ADDITION AND COVERRED PATIO PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 1/10/2024
- Issuing Office
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2023 | KHUONG TRUONG |
| Corrections Issued | 3/9/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 7/18/2023 | KHUONG TRUONG |
| Plan Check Approved | 11/16/2023 | KHUONG TRUONG |
| Issued | 1/10/2024 | APPLICANT |
| CofO in Progress | 4/14/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
| CofO Issued | 4/17/2025 | DEROLD HAUFF |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 4/8/2023 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 6/26/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/10/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/14/2024 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/18/2024 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 7/19/2024 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 7/19/2024 | Approved | THOMAS LOGRASSO |
| Sewer | 7/25/2024 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 7/25/2024 | Partial Approval | BRENDAN MORELLI |
| Wood Frame | 8/14/2024 | Conditional Approval | THOMAS LOGRASSO |
| Insulation | 8/27/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 8/27/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 9/5/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/21/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 2/21/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 2/21/2025 | Conditional Approval | WILLIAM SIERRA |
| Final | 2/21/2025 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 2/21/2025 | Approved | WILLIAM SIERRA |
| Green Building Final | 2/21/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 2/21/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 2/21/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 2/21/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | WILLIAM SIERRA |
| Smoke Detectors | 2/21/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/21/2025 | Partial Inspection | NICHOLAS LOPEZ |
| Green Building Final | 3/21/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Rough | 3/21/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Final | 3/27/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 3/27/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 4/11/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Green Building Final | 4/11/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Final | 4/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |