3122 W MADERA AVE 90039

Certificate Information: 3122 W MADERA AVE 90039

Application / Permit
23014-10000-00714
Plan Check / Job No.
B23LA03208
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Existing Garage conversion to ADU WITH ADDITION AND COVERRED PATIO PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 1/10/2024
Issuing Office
Current Status
CofO Issued on 4/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2023 APPLICANT
Assigned to Plan Check Engineer 3/8/2023 KHUONG TRUONG
Corrections Issued 3/9/2023 KHUONG TRUONG
Applicant returned to address corrections 7/18/2023 KHUONG TRUONG
Plan Check Approved 11/16/2023 KHUONG TRUONG
Issued 1/10/2024 APPLICANT
CofO in Progress 4/14/2025 NICHOLAS LOPEZ
Permit Finaled 4/17/2025 DEROLD HAUFF
CofO Issued 4/17/2025 DEROLD HAUFF
Permit Finaled 4/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 4/8/2023 ADRIAN SANCHEZ
Construction near power lines Cleared 6/26/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/10/2023 ADRIAN SANCHEZ
Sewer availability Cleared 10/10/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2024 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 6/18/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 6/18/2024 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 7/19/2024 Corrections Issued THOMAS LOGRASSO
Underground Mechanical 7/19/2024 Approved THOMAS LOGRASSO
Sewer 7/25/2024 Approved BRENDAN MORELLI
Underground Mechanical 7/25/2024 Partial Approval BRENDAN MORELLI
Wood Frame 8/14/2024 Conditional Approval THOMAS LOGRASSO
Insulation 8/27/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 8/27/2024 Partial Approval THOMAS LOGRASSO
Shower Pan 8/27/2024 Approved THOMAS LOGRASSO
Drywall Nailing 9/5/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 9/11/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 2/21/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 2/21/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 2/21/2025 Conditional Approval WILLIAM SIERRA
Final 2/21/2025 Corrections Issued WILLIAM SIERRA
Footing/Foundation/Slab 2/21/2025 Approved WILLIAM SIERRA
Green Building Final 2/21/2025 Corrections Issued WILLIAM SIERRA
Green Building Rough 2/21/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 2/21/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 2/21/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Ready WILLIAM SIERRA
Smoke Detectors 2/21/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 3/21/2025 Approved NICHOLAS LOPEZ
Final 3/21/2025 Partial Inspection NICHOLAS LOPEZ
Green Building Final 3/21/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Rough 3/21/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready NICHOLAS LOPEZ
Final 3/27/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/27/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 4/11/2025 Conditional Approval NICHOLAS LOPEZ
Green Building Final 4/11/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/11/2025 SGSOV Approved NICHOLAS LOPEZ
Final 4/14/2025 OK to Issue CofO NICHOLAS LOPEZ