4150 W NORMAL AVE 90029
Certificate Information: 4150 W NORMAL AVE 90029
- Application / Permit
- 23014-10000-00710
- Plan Check / Job No.
- B22LA26798
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan - CONVERT EXISTING GARAGE TO ADU AND ADDITION TO ADU PER 65852.2(E)(1)(D) (RIGHT)
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Current Status
- Issued on 9/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | STARR CHEN |
| Corrections Issued | 2/23/2023 | STARR CHEN |
| Quality Review Completed | 2/28/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 6/23/2023 | STARR CHEN |
| Plan Check Approved | 7/13/2023 | STARR CHEN |
| No Progress | 7/13/2023 | STARR CHEN |
| Plan Check Approved | 7/13/2023 | STARR CHEN |
| Plan Check Approved | 9/6/2023 | STARR CHEN |
| Issued | 9/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/22/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | JEANIE LAM |
| Sewer availability | Cleared | 5/23/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 6/5/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 6/5/2023 | GILBERT URREA |
| Grading Pre-Inspection | Cleared | 6/8/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Buildings And Structures Inc; Lic. No.: 563725-B | , |
| Contractor | Caldeco Inc; Lic. No.: 563725-B | , |
| Engineer | Quiaot,, Florentino V; Lic. No.: C38659 | 412 W 231ST ST CARSON, CA 90745 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2023 | Partial Inspection | ALIZAH MAYAGOITIA |