7411 N NEWCASTLE AVE 91335
Certificate Information: 7411 N NEWCASTLE AVE 91335
- Application / Permit
- 23014-10000-00702
- Plan Check / Job No.
- B23LA03123
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* 21'-4" X 18'-11" ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Current Status
- CofO Issued on 1/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | SELLA BENYAMIN |
| Corrections Issued | 2/23/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/20/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/28/2023 | SELLA BENYAMIN |
| Plan Check Approved | 3/31/2023 | SELLA BENYAMIN |
| Issued | 4/28/2023 | APPLICANT |
| CofO in Progress | 12/21/2023 | JEFFREY BULL |
| Permit Finaled | 1/2/2024 | JOHN JANSON |
| CofO Issued | 1/2/2024 | JOHN JANSON |
| Permit Finaled | 1/2/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/27/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: NA53256 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/20/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | JEFFREY BULL |
| Insulation | 6/26/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | No Access for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/17/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 8/17/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 8/17/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 8/17/2023 | Approved | JEFFREY BULL |
| Insulation | 8/21/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 8/25/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 12/20/2023 | Approved | JEFFREY BULL |
| Final | 12/20/2023 | OK to Issue CofO | JEFFREY BULL |
| HVAC-Final | 12/20/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 12/20/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 12/20/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 12/20/2023 | Approved | JEFFREY BULL |