3454 S SYCAMORE AVE 90016
Certificate Information: 3454 S SYCAMORE AVE 90016
- Application / Permit
- 23014-10000-00676
- Plan Check / Job No.
- B23LA02942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW COVERED DECK ATTACHED TO REAR OF EXISTING HOUSE
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2023 | GEORGE ALVAREZ |
| Corrections Issued | 2/28/2023 | GEORGE ALVAREZ |
| Building Plans Picked Up | 3/2/2023 | APPLICANT |
| Issued | 3/6/2023 | APPLICANT |
| CofO in Progress | 12/20/2024 | JOSE MACIAS |
| Permit Finaled | 12/26/2024 | DEROLD HAUFF |
| CofO Issued | 12/26/2024 | DEROLD HAUFF |
| Permit Finaled | 12/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 3/2/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mniarji,, Majd Sameer; Lic. No.: C93049 | 7812 VASSAR AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/13/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 3/20/2023 | Approved | JOSE AVILA |
| Deck | 7/27/2023 | Approved | ALIZAH MAYAGOITIA |
| Light Gage Steel Frame | 7/27/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/18/2023 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 8/18/2023 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/17/2024 | Approved | JOSE MACIAS |
| Final | 12/17/2024 | OK to Issue CofO | JOSE MACIAS |
| Green Building Final | 12/17/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 12/17/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 12/17/2024 | Approved | JOSE MACIAS |