8119 N LINDLEY AVE 91335
Certificate Information: 8119 N LINDLEY AVE 91335
- Application / Permit
- 23014-10000-00674
- Plan Check / Job No.
- B23LA00324
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERSION OF (E) GARAGE WITH NEW GROUND FLOOR ADDITION TO ADU PER LAMC 12.22 A.33 (c)-(d) , (g).
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Current Status
- CofO Issued on 6/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 2/20/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/2/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/10/2023 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 5/31/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 7/27/2023 | MARCELA FRANQUEZ |
| Issued | 7/27/2023 | APPLICANT |
| CofO in Progress | 5/21/2024 | JEFFREY BULL |
| CofO Issued | 6/18/2024 | JOHN JANSON |
| Permit Finaled | 6/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 6/27/2023 | ROGELIO CORTES |
| Stormwater Pollution Mitigatn | Cleared | 6/27/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | WALLIE JONG |
| Sewer availability | Cleared | 6/30/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/2/2023 | Approved | JEFFREY BULL |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 8/24/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Approved | JEFFREY BULL |
| Insulation | 9/18/2023 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/25/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 9/25/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 9/25/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/25/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 9/25/2023 | Approved | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 9/25/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | JEFFREY BULL |
| Insulation | 10/3/2023 | Approved | JEFFREY BULL |
| Shower Pan | 10/3/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 10/10/2023 | Approved | JEFFREY BULL |
| Final | 11/21/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 11/21/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 11/21/2023 | Approved | JEFFREY BULL |
| Final | 5/21/2024 | OK to Issue CofO | JEFFREY BULL |