5717 N BIANCA AVE 91316
Certificate Information: 5717 N BIANCA AVE 91316
- Application / Permit
- 23014-10000-00672
- Plan Check / Job No.
- B23LA02924
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 1 STORY SFD/ WITH ATTACHED GARAGE REMODEL AND ADDITION
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 3/13/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/29/2023 | FARUK SEZER |
| Applicant returned to address corrections | 5/1/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/3/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 5/5/2023 | CRYSTEL MAALOUF |
| Issued | 5/8/2023 | APPLICANT |
| CofO in Progress | 7/24/2024 | JON MCHUGH |
| Permit Finaled | 10/28/2024 | JOHN JANSON |
| CofO Issued | 10/28/2024 | JOHN JANSON |
| Permit Finaled | 10/28/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/5/2023 | LEE GUILBEAUX |
| ZI | Cleared | 4/5/2023 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 4/15/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 4/19/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 4/19/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Levin,, Vladimir; Lic. No.: C35001 | 11606 CHENAULT STR, UNIT 301 LOS ANGELES, CA 90049 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 6/13/2023 | Corrections Issued | SEAN WIRCH |
| PLUMBING-Rough | 6/13/2023 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 6/21/2023 | Approved | JEFFREY BULL |
| Insulation | 6/27/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 6/30/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | JON MCHUGH |
| Wood Frame | 8/24/2023 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 9/1/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Conditional Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 9/6/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 9/18/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 9/18/2023 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 9/18/2023 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 9/18/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 9/18/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 10/5/2023 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 10/5/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 10/5/2023 | Approved | JON MCHUGH |
| Deputy Drilled-In Anchors | 10/6/2023 | Conditional Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/6/2023 | Partial Approval | HORACE FULTZ |
| Interior/Exterior Lathing | 10/6/2023 | Partial Approval | MORRIS JACKSON |
| Insulation | 10/16/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 11/2/2023 | Approved | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 11/2/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 11/21/2023 | Approved | MORRIS JACKSON |
| Shower Pan | 11/21/2023 | Approved | MORRIS JACKSON |
| Final | 6/27/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 6/27/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 7/23/2024 | Approved | JON MCHUGH |
| Final | 7/23/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 7/23/2024 | Approved | JON MCHUGH |
| HVAC-Final | 7/23/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/23/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 7/23/2024 | Approved | JON MCHUGH |
| Deputy Drilled-In Anchors | 8/5/2024 | Partial Approval | SEAN WIRCH |