5660 E FAYETTE ST 90042

Certificate Information: 5660 E FAYETTE ST 90042

Application / Permit
23014-10000-00640
Plan Check / Job No.
B23LA02782
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(ePlan) PARTIAL DEMOLITION AND REBUILT WITH ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 5/18/2023
Issuing Office
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 YOUNG KIM
Corrections Issued 3/15/2023 YOUNG KIM
Quality Review Completed 3/15/2023 GARO TELMI
Applicant returned to address corrections 4/11/2023 YOUNG KIM
Plan Check Approved 5/3/2023 YOUNG KIM
Issued 5/18/2023 APPLICANT
CofO in Progress 2/28/2024 ALIZAH MAYAGOITIA
Permit Finaled 3/4/2024 DEROLD HAUFF
CofO Issued 3/4/2024 DEROLD HAUFF
Permit Finaled 3/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/20/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 3/28/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/29/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Dorier,, David Julienmichel; Lic. No.: S7064 950 S GRAND AVE 4TH FLOOR      LOS ANGELES, CA 90015

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/20/2023 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 7/20/2023 Approved CRAIG VAUGHAN
Wood Frame 8/31/2023 Partial Approval CRAIG VAUGHAN
Special/Order Compliance 10/2/2023 Partial Approval CRAIG VAUGHAN
Wood Frame 10/2/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/6/2023 Not Ready for Inspection ROY SPAULDING
Wood Frame 10/6/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 11/6/2023 Approved ROY SPAULDING
ELECTRICAL-Rough 11/20/2023 Approved ROY SPAULDING
HVAC-Rough 11/20/2023 Approved ROY SPAULDING
PLUMBING-Rough 11/20/2023 Corrections Issued ROY SPAULDING
Insulation 11/22/2023 Approved ROY SPAULDING
Drywall Nailing 12/1/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 2/21/2024 Approved ALIZAH MAYAGOITIA
Final 2/21/2024 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/21/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 2/21/2024 Approved ALIZAH MAYAGOITIA
Final 2/23/2024 Conditional Approval ALIZAH MAYAGOITIA
Final 2/26/2024 Conditional Approval ALIZAH MAYAGOITIA
Final 2/28/2024 OK to Issue CofO ALIZAH MAYAGOITIA