2502 N LAKE VIEW AVE 90039
Certificate Information: 2502 N LAKE VIEW AVE 90039
- Application / Permit
- 23014-10000-00639
- Plan Check / Job No.
- B23LA02781
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Proposed remodel of existing single story house including partial demolition and deck addition
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/1/2025
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2023 | KHUONG TRUONG |
| Corrections Issued | 3/7/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 4/20/2023 | DANIEL YIP |
| Plan Check Approved | 4/26/2023 | KHUONG TRUONG |
| Issued | 4/26/2023 | APPLICANT |
| Permit Finaled | 5/1/2025 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/8/2023 | RICARDO BOHORQUEZ |
| ZA Case | Cleared | 3/15/2023 | SPENCER WEJROWSKI |
| Grading Pre-Inspection | Cleared | 4/20/2023 | KHUONG TRUONG |
Contact Information
| Contractor | Highground Builders; Lic. No.: 1042579-B | , |
| Contractor | Highground Solutions Inc.; Lic. No.: 1042579-B | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: NA56881 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Partial Approval | THOMAS LOGRASSO |
| Pre-Inspection | 6/1/2023 | Partial Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 7/11/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/19/2023 | Approved | THOMAS LOGRASSO |
| Wood Frame | 8/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 6/3/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 7/26/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 9/25/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 9/25/2024 | Approved | LUIS CASTRO |
| Wood Frame | 9/25/2024 | Approved | LUIS CASTRO |
| Drywall Nailing | 10/15/2024 | Approved | LUIS CASTRO |
| Final | 4/1/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/1/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 4/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 5/1/2025 | Permit Finaled | HAMIK HARTOUNIAN |