3501 N ALGINET DR 91436

Certificate Information: 3501 N ALGINET DR 91436

Application / Permit
23014-10000-00617
Plan Check / Job No.
B23LA02651
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 1. Remodel existing SFD and addition to first and second story
Permit Issued
Issued on 5/13/2024
Issuing Office
Current Status
Issued on 5/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 MARCELA FRANQUEZ
Corrections Issued 4/1/2023 MARCELA FRANQUEZ
Quality Review Completed 4/7/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 6/20/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 7/31/2023 MARCELA FRANQUEZ
Plan Check Approved 9/11/2023 MARCELA FRANQUEZ
Issued 5/13/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/11/2023 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 4/11/2023 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 4/11/2023 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 4/11/2023 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 4/11/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 4/11/2023 NADER ISKANDER
Construction within easement Cleared 4/11/2023 NADER ISKANDER
Eng Process Fee Ord 176,300 Cleared 4/12/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 4/12/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 4/22/2023 KURT CORRAL
Low Impact Development (LID) Cleared 6/6/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/7/2023 DAGOVERTO GUERRERO
Certificate of Compliance Cleared 6/27/2023 OLGA AYALA
Specific Plan Cleared 6/27/2023 OLGA AYALA
ZI Cleared 6/27/2023 OLGA AYALA
GPI Written Notices Cleared 7/31/2023 MARCELA FRANQUEZ
Grading Pre-Inspection Cleared 7/31/2023 MARCELA FRANQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316
Engineer Noorzay,, Maihan; Lic. No.: GE3085 16531 ORANGEHAVEN LANE      RIVERSIDE, CA 92503

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/10/2024 Approved THOMAS FINNILA
Piling/Pier/Caisson 9/6/2024 Corrections Issued THOMAS FINNILA
Piling/Pier/Caisson 9/7/2024 Partial Inspection MISAEL ESPARZA
Piling/Pier/Caisson 9/10/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 9/12/2024 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 9/24/2024 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 10/21/2024 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 12/19/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 12/20/2024 Corrections Issued THOMAS FINNILA
Pre-Inspection 1/27/2025 Approved THOMAS FINNILA
Sewer 4/8/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 4/14/2025 Conditional Approval JOHN COLEMAN
PLUMBING-Rough 4/14/2025 Partial Approval JOHN COLEMAN
Sewer 4/14/2025 Partial Approval JOHN COLEMAN
Wood Frame 4/17/2025 Partial Approval JOHN COLEMAN
Underground Mechanical 4/22/2025 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 5/12/2025 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 6/10/2025 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/17/2025 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 11/10/2025 Corrections Issued THOMAS FINNILA
Green Building Rough 11/10/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 12/22/2025 Not Ready for Inspection SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 12/22/2025 Corrections Issued SEAN WIRCH
ELECTRICAL-Rough 1/9/2026 Corrections Issued THOMAS FINNILA
HVAC-Rough 1/9/2026 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/12/2026 Partial Approval MORRIS JACKSON
PLUMBING-Rough 1/16/2026 Corrections Issued THOMAS FINNILA
HVAC-Rough 3/9/2026 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/10/2026 Approved DAVID SCANTLIN
Green Building Rough 3/10/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/11/2026 Partial Approval ROBERT GOLD