705 W 167TH ST 90247
Certificate Information: 705 W 167TH ST 90247
- Application / Permit
- 23014-10000-00556
- Plan Check / Job No.
- B23LA02293
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) DETACHED GARAGE TO (N) ADU WITH ADDITION PER STATE LAW PER WFPP
- Permit Issued
- Issued on 3/15/2023
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2023 | JOSEPH RAFOLS |
| Corrections Issued | 2/23/2023 | MINA HABILI |
| Applicant returned to address corrections | 3/9/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 3/14/2023 | GEORGE ALVAREZ |
| Issued | 3/15/2023 | SHANNON HAAS |
| CofO in Progress | 9/21/2023 | JAMES CHAVEZ |
| Permit Finaled | 9/21/2023 | ANSON MAGLASANG |
| CofO Issued | 9/21/2023 | ANSON MAGLASANG |
| Permit Finaled | 9/21/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2023 | ANA SORIANO |
| Miscellaneous | Cleared | 2/28/2023 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 2/28/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | ANA SORIANO |
| Sewer availability | Cleared | 3/7/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2023 | Conditional Approval | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 4/7/2023 | Conditional Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 4/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Underground Mechanical | 4/10/2023 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 4/13/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/5/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 5/5/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/23/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 5/23/2023 | Corrections Issued | JAMES CHAVEZ |
| Underground Mechanical | 5/23/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/26/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 5/26/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 5/26/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 5/26/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 5/26/2023 | Approved | JAMES CHAVEZ |
| Insulation | 6/7/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/13/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 6/13/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 6/15/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | JAMES CHAVEZ |
| Final | 8/10/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/10/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 8/10/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Final | 8/10/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Rough | 8/10/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 8/10/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 8/16/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Final | 9/5/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 9/12/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 9/12/2023 | Approved | JAMES CHAVEZ |
| MERV13>=Final | 9/12/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 9/12/2023 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 9/12/2023 | Approved | JAMES CHAVEZ |