2046 N AMES ST 90027
Certificate Information: 2046 N AMES ST 90027
- Application / Permit
- 23014-10000-00551
- Plan Check / Job No.
- B22LA26951
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) STORAGE TO 2-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | DANIEL YIP |
| Corrections Issued | 3/8/2023 | DANIEL YIP |
| Quality Review Completed | 3/8/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/28/2023 | DANIEL YIP |
| Plan Check Approved | 7/11/2023 | DANIEL YIP |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 10/21/2025 | ENRIQUE MIRELES |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
| CofO Issued | 10/23/2025 | DEROLD HAUFF |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/8/2023 | DANIEL YIP |
| Address approval | Cleared | 3/18/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 3/18/2023 | CINDY QI |
| Street Frontage | Cleared | 3/18/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | CINDY QI |
| Sewer availability | Cleared | 3/20/2023 | CINDY QI |
| Hydrant and Access approval | Cleared | 3/30/2023 | KURT CORRAL |
| Miscellaneous | Cleared | 5/30/2023 | ALBERT TAM |
| Construction near power lines | Cleared | 6/29/2023 | NADER ISKANDER |
Contact Information
| Contractor | Youssef Construction Inc; Lic. No.: 938042-B | , |
| Engineer | Naeem,, Samer Atef; Lic. No.: NA88038 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/19/2023 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/16/2023 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/20/2024 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/20/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 2/20/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 2/20/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/20/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 2/20/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/8/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/8/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/8/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 4/23/2024 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/23/2024 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 4/23/2024 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 5/6/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/16/2024 | Corrections Issued | ENRIQUE MIRELES |
| Shower Pan | 5/29/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Shower Pan | 5/31/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 12/26/2024 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/31/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 12/31/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 1/10/2025 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 1/28/2025 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 2/4/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/2/2025 | Approved | ENRIQUE MIRELES |
| Final | 7/2/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/2/2025 | Approved | ENRIQUE MIRELES |
| Green Building Final | 7/2/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/2/2025 | Approved | ENRIQUE MIRELES |
| Final | 7/24/2025 | Corrections Issued | ENRIQUE MIRELES |
| Final | 7/29/2025 | Corrections Issued | JOSE MACIAS |
| Final | 10/6/2025 | OK to Issue CofO | ENRIQUE MIRELES |