434 N OGDEN DR 90036
Certificate Information: 434 N OGDEN DR 90036
- Application / Permit
- 23014-10000-00546
- Plan Check / Job No.
- B23LA02257
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (7) Garage - Private
- Work Description
- ADDITION TO (E) DETACHED GARAGE
- Permit Issued
- Issued on 6/16/2023
- Issuing Office
- Current Status
- Issued on 6/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | GEORGE ALVAREZ |
| Corrections Issued | 2/9/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 6/9/2023 | FERNANDO FLORES |
| Issued | 6/16/2023 | APPLICANT |
Permit Application Clearance Information
| Historic monument | Cleared | 4/21/2023 | MAX LODER |
| Tenant Habitability Plan | Cleared | 5/2/2023 | RICARDO BOHORQUEZ |
| Construction near power lines | Cleared | 5/3/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/3/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | NAZILA NOORIFAR |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | NAZILA NOORIFAR |
| Public Works-Open Permits | Cleared | 5/23/2023 | NAZILA NOORIFAR |
Contact Information
| Contractor | En Construction Services Inc; Lic. No.: 1105442-B | 2346 SELBY AVE LOS ANGELES, CA 90064 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 11/1/2024 | Approved | CHRISTOPHER BLACKWOOD |
| Wood Frame | 11/1/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 11/18/2024 | Approved | CHRISTOPHER BLACKWOOD |
| Final | 2/7/2025 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 2/7/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Barrier | 2/7/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Subgrade | 2/7/2025 | Approved | MARTIN TAVITIAN |
| Smoke Detectors | 2/7/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 2/7/2025 | Approved | MARTIN TAVITIAN |
| Final | 2/12/2025 | Conditional Approval | MARTIN TAVITIAN |