10649 N WOODWARD AVE 91040

Certificate Information: 10649 N WOODWARD AVE 91040

Application / Permit
23014-10000-00523
Plan Check / Job No.
B23LA02169
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT (E) GARAGE TO 2-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 5/2/2024
Issuing Office
Metro
Current Status
Issued on 5/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/8/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 DANIEL YIP
Corrections Issued 3/7/2023 DANIEL YIP
Quality Review Completed 3/10/2023 KEN GILL
Applicant returned to address corrections 5/31/2023 DANIEL YIP
Applicant returned to address corrections 11/14/2023 DANIEL YIP
Plan Check Approved 12/6/2023 DANIEL YIP
Issued 5/2/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/21/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/25/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 7/27/2023 ALEXANDER HELFER
Low Impact Development (LID) Cleared 10/26/2023 LUIS LUVANO
Sewer availability Cleared 10/27/2023 LEE GUILBEAUX
GPI Written Notices Cleared 12/6/2023 DANIEL YIP
Roof/Waste drainage to street Cleared 12/6/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 6/12/2024 Partial Approval WILLIAM WREN
Deputy Drilled-In Anchors 6/13/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 6/21/2024 Not Ready for Inspection WILLIAM WREN
Wood Frame 7/16/2024 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 7/19/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Approval WILLIAM WREN
PLUMBING-Rough 1/7/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 1/15/2025 Partial Approval WILLIAM WREN
Special/Order Compliance 1/15/2025 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 6/6/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 6/6/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Approved WILLIAM WREN
Green Building Rough 6/6/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 7/2/2025 Approved LOUIS ESCOTO
HVAC-Rough 9/5/2025 Approved WILLIAM WREN
Insulation 9/5/2025 Approved WILLIAM WREN
Drywall Nailing 9/17/2025 Approved WILLIAM WREN
Shower Pan 1/8/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 2/25/2026 Approved NICHOLAS TROWBRIDGE