14606 W MARGATE ST 91411
Certificate Information: 14606 W MARGATE ST 91411
- Application / Permit
- 23014-10000-00506
- Plan Check / Job No.
- B23LA02074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: PROPOSED ADDITION TO EXISTING SINGLE FAMILY DWELLING TO CREATE MUD ROOM, BATHROOM, AND MASTER BEDROOM, SCOPE TO ALSO INCLUDE NEW PATIO COVER, ENLARGE EXISTING ATTACHED GARAGE.
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | MICHAEL LOPEZ |
| Corrections Issued | 3/15/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 3/22/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/19/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/26/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 5/30/2024 | MICHAEL LOPEZ |
| Issued | 6/5/2024 | APPLICANT |
| CofO in Progress | 5/7/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| CofO Issued | 6/3/2025 | RUBEN SALAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 11/30/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/28/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 1/2/2024 | CARLOS RAMIREZ |
| ZA Case | Cleared | 1/4/2024 | YINGSHI HUANG |
| ZA Case | Cleared | 1/4/2024 | YINGSHI HUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/3/2024 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/29/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 8/12/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 8/15/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/4/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 11/4/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 11/4/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 11/13/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 11/18/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 11/20/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 12/18/2024 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 12/20/2024 | Corrections Issued | JACK KARGODORIAN |
| Shower Pan | 12/23/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/30/2024 | Conditional Approval | JOSE AVILA |
| Special/Order Compliance | 12/30/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 3/18/2025 | Approved | JACK KARGODORIAN |
| Final | 3/18/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 3/18/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/18/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2025 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 3/18/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/5/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/5/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 5/5/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/5/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Approved | JENNIFER RABUCHIN |