16703 S ESTRELLA AVE Unit C 90247
Certificate Information: 16703 S ESTRELLA AVE Unit C 90247
- Application / Permit
- 23014-10000-00497
- Plan Check / Job No.
- B23LA02022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 20'-3" X 25'-1" ACCESSORY DWELLING UNIT ABOVE (E) DETACHED 2-CAR GARAGE WITH EXTERIOR STAIRS PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 2/19/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/10/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/28/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 8/26/2024 | ALEC MOUSAKHANIAN |
| Issued | 9/4/2024 | APPLICANT |
| CofO in Progress | 2/19/2026 | BEN MOLSTAD |
| Permit Finaled | 2/20/2026 | ANSON MAGLASANG |
| CofO Issued | 2/20/2026 | ANSON MAGLASANG |
| Permit Finaled | 2/20/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | HUGO LOPEZ |
| ZA Case | Cleared | 4/7/2023 | MAYELA VILLA |
| Stormwater Pollution Mitigatn | Cleared | 12/26/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/18/2024 | KHAING AYE |
| Sewer availability | Cleared | 6/17/2024 | ERIK BEASLEY |
| Construction near power lines | Cleared | 7/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Maderas Construction Inc; Lic. No.: 911252-B | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2025 | Conditional Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 5/29/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/2/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 6/2/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 6/2/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Deputy Wood Construction | 6/10/2025 | Conditional Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/26/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 6/26/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 6/26/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 6/26/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 6/26/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 7/1/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | JOHN KLARIN |
| Green Building Rough | 7/7/2025 | Approved | JOHN KLARIN |
| Insulation | 7/11/2025 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 7/11/2025 | Partial Approval | BEN MOLSTAD |
| Drywall Nailing | 7/15/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 11/3/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 11/3/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 11/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 11/3/2025 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 11/3/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 11/3/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 11/3/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 11/13/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 11/13/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 11/14/2025 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 2/19/2026 | Approved | BEN MOLSTAD |
| Final | 2/19/2026 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 2/19/2026 | Approved | BEN MOLSTAD |
| HVAC-Final | 2/19/2026 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 2/19/2026 | Approved | BEN MOLSTAD |