1920-1922 S BEDFORD ST 90034
Certificate Information: 1920-1922 S BEDFORD ST 90034
- Application / Permit
- 23014-10000-00474
- Plan Check / Job No.
- B23LA01932
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE AND STORAGE INTO A NEW ACCESSORY DWELLING UNIT. NEW 2ND FLOOR ADDITION.
- Permit Issued
- Issued on 3/3/2023
- Issuing Office
- Current Status
- CofO Issued on 12/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | KEVIN MORALES |
| Corrections Issued | 2/17/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 2/27/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 2/28/2023 | KEVIN MORALES |
| Plan Check Approved | 3/2/2023 | KEVIN MORALES |
| Issued | 3/3/2023 | APPLICANT |
| CofO in Progress | 12/4/2023 | MEL KHACHATOURIAN |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
| CofO Issued | 12/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2023 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/24/2023 | JEANETTE VONG |
| Sewer availability | Cleared | 2/24/2023 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: NA50820 | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 5/16/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/18/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 5/18/2023 | Approved | JEREMY TODD |
| Piling/Pier/Caisson | 5/18/2023 | Approved | JEREMY TODD |
| Sewer | 5/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Rough-Elec/Plmb/HVAC | 7/3/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/6/2023 | Corrections Issued | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 7/6/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 7/10/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 7/10/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 7/11/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 7/14/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 7/20/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | MEL KHACHATOURIAN |
| Final | 11/3/2023 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/3/2023 | Approved | MEL KHACHATOURIAN |
| Final | 12/5/2023 | OK to Issue CofO | MEL KHACHATOURIAN |