1920-1922 S BEDFORD ST 90034

Certificate Information: 1920-1922 S BEDFORD ST 90034

Application / Permit
23014-10000-00474
Plan Check / Job No.
B23LA01932
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE AND STORAGE INTO A NEW ACCESSORY DWELLING UNIT. NEW 2ND FLOOR ADDITION.
Permit Issued
Issued on 3/3/2023
Issuing Office
Current Status
CofO Issued on 12/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 KEVIN MORALES
Corrections Issued 2/17/2023 KEVIN MORALES
Applicant returned to address corrections 2/27/2023 KEVIN MORALES
Applicant returned to address corrections 2/28/2023 KEVIN MORALES
Plan Check Approved 3/2/2023 KEVIN MORALES
Issued 3/3/2023 APPLICANT
CofO in Progress 12/4/2023 MEL KHACHATOURIAN
Permit Finaled 12/6/2023 DANIEL ORRANTE
CofO Issued 12/6/2023 DANIEL ORRANTE
Permit Finaled 12/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/24/2023 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/24/2023 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/24/2023 JEANETTE VONG
Sewer availability Cleared 2/24/2023 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: NA50820       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/15/2023 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 5/16/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved JEREMY TODD
Footing/Foundation/Slab 5/18/2023 Approved JEREMY TODD
Piling/Pier/Caisson 5/18/2023 Approved JEREMY TODD
Sewer 5/18/2023 Not Ready for Inspection JEREMY TODD
Rough-Elec/Plmb/HVAC 7/3/2023 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 7/6/2023 Corrections Issued ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 7/6/2023 Approved ARAM AVEDISIAN
Insulation 7/10/2023 Not Ready for Inspection ARAM AVEDISIAN
Wood Frame 7/10/2023 Approved ARAM AVEDISIAN
Shower Pan 7/11/2023 Approved ARAM AVEDISIAN
Insulation 7/14/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/14/2023 Partial Approval ARAM AVEDISIAN
Drywall Nailing 7/20/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/3/2023 Approved MEL KHACHATOURIAN
Final 11/3/2023 Corrections Issued MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 11/3/2023 Approved MEL KHACHATOURIAN
Final 12/5/2023 OK to Issue CofO MEL KHACHATOURIAN