10221 W WILKINS AVE 90024

Certificate Information: 10221 W WILKINS AVE 90024

Application / Permit
23014-10000-00462
Plan Check / Job No.
B23LA01876
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) 2-STORY SFD AND REMODEL.
Permit Issued
Issued on 3/4/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 VIVIAN LAO
Corrections Issued 2/24/2023 VIVIAN LAO
Quality Review Completed 3/1/2023 KEN GILL
Building Plans Picked Up 3/6/2023 APPLICANT
Plan Check Approved 4/25/2023 VIVIAN LAO
Issued 3/4/2024 APPLICANT
CofO in Progress 5/5/2025 DANIEL VERA
Permit Finaled 5/15/2025 RICHARD STEINBACH
CofO Issued 5/15/2025 RICHARD STEINBACH
Permit Finaled 5/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/10/2023 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 4/10/2023 DENNIS BRAGIN
Sewer availability Cleared 4/10/2023 DENNIS BRAGIN
Grading Pre-Inspection Cleared 4/19/2023 VASIL MIHALEV

Contact Information

Architect Oreck,, Kevin Robert; Lic. No.: C23895 1008 LARKER AVE      LOS ANGELES, CA 90042
Contractor Fischer Joel Construction Inc; Lic. No.: 528992-B PO BOX 341338      LOS ANGELES, CA 90064
Engineer Chung,, Jun Sung; Lic. No.: S2766 15909 CARMENIA DR      WHITTIER, CA 90603

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/5/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 6/5/2024 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 6/5/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 6/5/2024 Not Ready for Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 6/28/2024 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/28/2024 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 7/11/2024 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/29/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 7/30/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 8/6/2024 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 8/6/2024 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 8/26/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 8/26/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/26/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 8/26/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 9/5/2024 Approved STEPHANIE SWANSON
Green Building Rough 9/5/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 9/5/2024 Partial Approval STEPHANIE SWANSON
Shower Pan 9/5/2024 Partial Approval STEPHANIE SWANSON
Insulation 9/6/2024 Approved STEPHANIE SWANSON
Drywall Nailing 9/11/2024 Approved STEPHANIE SWANSON
PLUMBING-Rough 9/11/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 9/18/2024 Approved MICHAEL ALLEN
Shower Pan 9/18/2024 Approved MICHAEL ALLEN
Final 1/30/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 1/30/2025 Approved STEPHANIE SWANSON
Green Building Final 1/30/2025 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 1/30/2025 Corrections Issued STEPHANIE SWANSON
Final 3/19/2025 Not Ready for Inspection DANIEL VERA
Smoke Detectors 3/19/2025 Approved DANIEL VERA
Final 5/5/2025 OK to Issue CofO DANIEL VERA
Service/Power Release 5/5/2025 Approved DANIEL VERA