8420 S READING AVE 90045

Certificate Information: 8420 S READING AVE 90045

Application / Permit
23014-10000-00449
Plan Check / Job No.
B23LA01807
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to rear of existing 1-story single family dwelling. All work per engineer "COMPLY WITH DEPARTMENT ORDER effective date 07/06/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/11/2023
Issuing Office
Current Status
CofO Issued on 10/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 VICTOR CHEN
Corrections Issued 2/6/2023 VICTOR CHEN
Applicant returned to address corrections 2/23/2023 ZAW HAN
Plan Check Approved 3/10/2023 ZAW HAN
Issued 3/11/2023 APPLICANT
CofO in Progress 4/17/2024 ANDREW BEELI
Permit Finaled 10/9/2024 CLAUDIO MORENO
CofO Issued 10/9/2024 CLAUDIO MORENO
Permit Finaled 10/9/2024 CLAUDIO MORENO

Permit Application Clearance Information

Specific Plan Cleared 2/7/2023 ALESSANDRO MERCURI
Grading Pre-Inspection Cleared 2/17/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 3/6/2023 JENSON LEE
Sewer availability Cleared 3/6/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 3/8/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2023 Not Ready for Inspection ANDREW BEELI
Deputy Drilled-In Anchors 6/9/2023 Partial Approval ANDREW BEELI
Footing/Foundation/Slab 6/16/2023 Approved ANDREW BEELI
Underground Mechanical 6/23/2023 Approved ANDREW BEELI
BUILDING-Rough-Frame 7/17/2023 Corrections Issued JOHN MATTILLO
ELECTRICAL-Rough 7/17/2023 Approved JOHN MATTILLO
HVAC-Rough 7/17/2023 Partial Approval JOHN MATTILLO
PLUMBING-Rough 7/17/2023 Approved JOHN MATTILLO
BUILDING-Rough-Frame 7/25/2023 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Rough 7/25/2023 Approved ANDREW BEELI
HVAC-Rough 7/25/2023 Corrections Issued ANDREW BEELI
Sewer 7/25/2023 Approved ANDREW BEELI
BUILDING-Rough-Frame 8/8/2023 Approved ANDREW BEELI
HVAC-Rough 8/8/2023 Approved ANDREW BEELI
Insulation 8/11/2023 Approved JEREMY TODD
Drywall Nailing 8/16/2023 Approved ANDREW BEELI
Final 10/20/2023 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved ANDREW BEELI
Smoke Detectors 10/20/2023 Approved ANDREW BEELI
ELECTRICAL-Final 10/24/2023 Approved ANDREW BEELI
Final 10/24/2023 Partial Approval ANDREW BEELI
HVAC-Final 10/24/2023 Approved ANDREW BEELI
PLUMBING-Final 10/24/2023 Approved ANDREW BEELI
Service/Power Release 10/24/2023 Approved ANDREW BEELI
Verify Rec and Parks Fee Memo 10/24/2023 Partial Approval ANDREW BEELI
Final 4/15/2024 Partial Approval ANDREW BEELI
Final 4/17/2024 OK to Issue CofO ANDREW BEELI