1610 S ELLSMERE AVE 90019
Certificate Information: 1610 S ELLSMERE AVE 90019
- Application / Permit
- 23014-10000-00426
- Plan Check / Job No.
- B23LA01666
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 521 SQ FT SECOND STORY ADDITION TO (E) 983 SQ FT SFD
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | JAD BASMA |
| Corrections Issued | 2/21/2023 | JAD BASMA |
| Quality Review Completed | 3/2/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/9/2023 | APPLICANT |
| Plan Check Approved | 9/19/2023 | JAD BASMA |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 9/25/2025 | ARTHUR NEGRETE |
| Permit Finaled | 9/29/2025 | DEROLD HAUFF |
| CofO Issued | 9/29/2025 | DEROLD HAUFF |
| Permit Finaled | 9/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/10/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/10/2023 | ADRIAN SANCHEZ |
| Stormwater Pollution Mitigatn | Cleared | 9/6/2023 | ROGELIO CORTES |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2023 | CELINA MORENO |
Contact Information
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2024 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/15/2024 | Partial Approval | STUART CHAPMAN |
| METHANE-Barrier | 2/15/2024 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 2/15/2024 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 2/26/2024 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/26/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 7/2/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/25/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Approved | ARTHUR NEGRETE |
| Shower Pan | 10/1/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Special/Order Compliance | 10/18/2024 | Corrections Issued | RONNIE MINDANAO |
| Deputy Wood Construction | 10/24/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/29/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 10/29/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 11/4/2024 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 11/4/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 11/7/2024 | Partial Approval | ARTHUR NEGRETE |
| PLUMBING-Rough | 11/7/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 11/13/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 11/20/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 1/2/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | NICHOLAS LOPEZ |
| Shower Pan | 1/29/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 4/23/2025 | Approved | ARTHUR NEGRETE |
| Final | 4/23/2025 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Final | 4/23/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 4/23/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Final | 4/23/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 4/23/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 4/23/2025 | Approved | ARTHUR NEGRETE |
| Final | 5/2/2025 | Partial Approval | ARTHUR NEGRETE |
| Green Building Final | 5/2/2025 | Approved | ARTHUR NEGRETE |
| Pool/Spa Cover | 5/2/2025 | Approved | ARTHUR NEGRETE |
| Final | 5/13/2025 | Partial Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/4/2025 | Approved | ARTHUR NEGRETE |
| Final | 8/4/2025 | Partial Approval | ARTHUR NEGRETE |
| HVAC-Final | 8/4/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 8/4/2025 | Approved | ARTHUR NEGRETE |
| Final | 9/24/2025 | OK to Issue CofO | ARTHUR NEGRETE |