2018 W 74TH ST 90047
Certificate Information: 2018 W 74TH ST 90047
- Application / Permit
- 23014-10000-00423
- Plan Check / Job No.
- B23LA01660
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 23'-5"x42'-8" ADU addtion to existing detached garage per WFPP (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2023 | VICTOR CHEN |
| Corrections Issued | 2/6/2023 | VICTOR CHEN |
| Building Plans Picked Up | 5/31/2023 | APPLICANT |
| Plan Check Approved | 6/6/2023 | MICHAEL LANZONE |
| Issued | 6/6/2023 | APPLICANT |
| CofO in Progress | 12/11/2023 | ENRIQUE MIRELES |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
| CofO Issued | 12/14/2023 | DEROLD HAUFF |
| Permit Finaled | 12/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/8/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/8/2023 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 6/6/2023 | LUIS LUVANO |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/29/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/12/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/20/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/20/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/26/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/26/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/31/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/30/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/30/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/8/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/8/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 9/8/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/8/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/13/2023 | Approved | MICHAEL LEWIS |
| Insulation | 9/28/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/4/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/18/2023 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 10/18/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 10/18/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 10/24/2023 | Corrections Issued | ENRIQUE MIRELES |
| Sewer | 10/26/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 11/13/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/13/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 11/13/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 11/13/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/13/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/13/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/29/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 12/4/2023 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Final | 12/6/2023 | Conditional Approval | ENRIQUE MIRELES |
| HVAC-Final | 12/6/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/6/2023 | Approved | ENRIQUE MIRELES |
| Final | 12/8/2023 | OK to Issue CofO | ENRIQUE MIRELES |