2018 W 74TH ST 90047

Certificate Information: 2018 W 74TH ST 90047

Application / Permit
23014-10000-00423
Plan Check / Job No.
B23LA01660
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
23'-5"x42'-8" ADU addtion to existing detached garage per WFPP (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 6/6/2023
Issuing Office
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2023 APPLICANT
Assigned to Plan Check Engineer 2/4/2023 VICTOR CHEN
Corrections Issued 2/6/2023 VICTOR CHEN
Building Plans Picked Up 5/31/2023 APPLICANT
Plan Check Approved 6/6/2023 MICHAEL LANZONE
Issued 6/6/2023 APPLICANT
CofO in Progress 12/11/2023 ENRIQUE MIRELES
Permit Finaled 12/14/2023 DEROLD HAUFF
CofO Issued 12/14/2023 DEROLD HAUFF
Permit Finaled 12/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/8/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/8/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 3/8/2023 ADRIAN SANCHEZ
Sewer availability Cleared 3/8/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 6/6/2023 LUIS LUVANO

Contact Information

Contractor Daniel Pascuale; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/29/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 7/12/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/20/2023 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 7/20/2023 No Access for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/26/2023 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 7/26/2023 No Access for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/27/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/31/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/31/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Approved ENRIQUE MIRELES
Green Building Rough 8/30/2023 Approved ENRIQUE MIRELES
HVAC-Rough 8/30/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 9/8/2023 Approved ENRIQUE MIRELES
Green Building Rough 9/8/2023 Approved ENRIQUE MIRELES
HVAC-Rough 9/8/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 9/8/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/13/2023 Approved MICHAEL LEWIS
Insulation 9/28/2023 Approved ENRIQUE MIRELES
Drywall Nailing 10/4/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/18/2023 Approved ENRIQUE MIRELES
Pre-Inspection 10/18/2023 Approved ENRIQUE MIRELES
Shower Pan 10/18/2023 Approved ENRIQUE MIRELES
Underground Mechanical 10/24/2023 Corrections Issued ENRIQUE MIRELES
Sewer 10/26/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/13/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 11/13/2023 Approved ENRIQUE MIRELES
Final 11/13/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 11/13/2023 Approved ENRIQUE MIRELES
HVAC-Final 11/13/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 11/13/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 11/13/2023 Approved ENRIQUE MIRELES
Final 11/29/2023 Corrections Issued ENRIQUE MIRELES
Final 12/4/2023 Partial Inspection DAVID FEILER
ELECTRICAL-Final 12/6/2023 Conditional Approval ENRIQUE MIRELES
HVAC-Final 12/6/2023 Approved ENRIQUE MIRELES
Service/Power Release 12/6/2023 Approved ENRIQUE MIRELES
Final 12/8/2023 OK to Issue CofO ENRIQUE MIRELES