3748 S 6TH AVE 90018

Certificate Information: 3748 S 6TH AVE 90018

Application / Permit
23014-10000-00408
Plan Check / Job No.
B23LA01571
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION AT REAR OF (E) DETACHED GARAGE, ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 12/29/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 6/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2023 APPLICANT
Assigned to Plan Check Engineer 1/31/2023 STANLEY RAAP
Corrections Issued 1/31/2023 STANLEY RAAP
Applicant returned to address corrections 5/31/2023 WEIJIAN HUANG
Plan Check Approved 6/27/2023 MINA HABILI
Issued 6/28/2023 APPLICANT
CofO in Progress 10/18/2024 WILLIAM MICHALAK
CofO Issued 3/5/2025 CLAUDIO MORENO
Permit Finaled 3/5/2025 CLAUDIO MORENO

Permit Application Clearance Information

Construction near power lines Cleared 5/7/2023 RIDWAN HARDY
Construction within easement Cleared 5/7/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/30/2023 HUGO LOPEZ
Roof/Waste drainage to street Cleared 5/30/2023 HUGO LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/24/2023 Corrections Issued GLEN RAND
Pre-Inspection 9/7/2023 Corrections Issued KIM DOEPPING
Wood Frame 10/11/2023 Corrections Issued WILLIAM MICHALAK
Wood Frame 11/22/2023 Not Ready for Inspection WILLIAM MICHALAK
Wood Frame 11/28/2023 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 1/9/2024 Approved WILLIAM MICHALAK
Drywall Nailing 6/12/2024 Approved WILLIAM MICHALAK
Final 6/12/2024 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 6/12/2024 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 6/12/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 7/26/2024 Corrections Issued WILLIAM MICHALAK
Smoke Detectors 7/30/2024 Approved WILLIAM MICHALAK
Final 10/18/2024 OK to Issue CofO WILLIAM MICHALAK