6027 W 76TH PL 90045
Certificate Information: 6027 W 76TH PL 90045
- Application / Permit
- 23014-10000-00369
- Plan Check / Job No.
- B23LA01421
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- Single story addition to bedroom. New bathroom.
- Permit Issued
- Issued on 3/31/2023
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | ZAW HAN |
| Corrections Issued | 2/11/2023 | DANIEL SANJUAN |
| Applicant returned to address corrections | 3/18/2023 | ZAW HAN |
| Plan Check Approved | 3/24/2023 | DANIEL SANJUAN |
| Issued | 3/31/2023 | APPLICANT |
| CofO in Progress | 3/14/2024 | BOBBY KEY |
| Permit Finaled | 3/20/2024 | DANIEL ORRANTE |
| CofO Issued | 3/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/16/2023 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 3/20/2023 | JASON NG |
| CPC | Cleared | 3/21/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 3/21/2023 | DALIA MOKAYED |
| Grading Pre-Inspection | Cleared | 3/24/2023 | DANIEL SANJUAN |
Contact Information
| Architect | Pribyl,, Steven Victor; Lic. No.: NA14048 | , |
| Contractor | E 2 W B; Lic. No.: 1041891-B | , |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2023 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/23/2023 | Approved | BOBBY KEY |
| Wood Frame | 6/13/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/26/2023 | Partial Approval | BOBBY KEY |
| Wood Frame | 6/26/2023 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 8/2/2023 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 9/21/2023 | Conditional Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 9/25/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/25/2023 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 10/12/2023 | Approved | BOBBY KEY |
| Insulation | 10/12/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 10/12/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 10/12/2023 | Approved | BOBBY KEY |
| Insulation | 10/23/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/23/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/26/2023 | Partial Approval | TEMISTOCLES CAAL |
| Drywall Nailing | 10/26/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/9/2024 | Approved | BOBBY KEY |
| Shower Pan | 1/9/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/16/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 3/14/2024 | Approved | BOBBY KEY |
| Final | 3/14/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 3/14/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/14/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 3/14/2024 | Approved | BOBBY KEY |
| Smoke Detectors | 3/14/2024 | Approved | BOBBY KEY |