2158 W 77TH ST 90047
Certificate Information: 2158 W 77TH ST 90047
- Application / Permit
- 23014-10000-00343
- Plan Check / Job No.
- B23LA01271
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ROOM ADDITION ONTO EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2023 | ZAW HAN |
| Corrections Issued | 1/30/2023 | ZAW HAN |
| Building Plans Picked Up | 1/31/2023 | APPLICANT |
| Applicant returned to address corrections | 6/21/2023 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/28/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 7/10/2023 | VICTOR CHEN |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 12/17/2024 | AMIR NAZARIAN |
| Permit Finaled | 12/26/2024 | DEROLD HAUFF |
| CofO Issued | 12/26/2024 | DEROLD HAUFF |
| Permit Finaled | 12/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 2/15/2023 | STEVE MELGAR |
| Sewer availability | Cleared | 2/15/2023 | STEVE MELGAR |
Contact Information
| Contractor | Eco Star Enterprises Llc; Lic. No.: 1060049-B | 3711 LONG BEACH BLVD STE 713 LONG BEACH, CA 90807 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/25/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/28/2023 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 11/28/2023 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/1/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/18/2023 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 12/18/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Underground Mechanical | 12/22/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 1/31/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/13/2024 | Approved | JOSH MEISTER |
| HVAC-Rough | 3/22/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 3/28/2024 | Conditional Approval | JOSE MACIAS |
| Shower Pan | 3/28/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 4/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/3/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 4/3/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 4/5/2024 | Approved | JOSE MACIAS |
| Insulation | 4/12/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 4/29/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 4/29/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 4/29/2024 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 5/20/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 7/2/2024 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 7/22/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Final | 10/15/2024 | Conditional Approval | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Smoke Detectors | 10/15/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 11/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Green Building Final | 11/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Final | 11/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Final | 11/13/2024 | Conditional Approval | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 11/13/2024 | SGSOV Approved | AMIR NAZARIAN |
| ELECTRICAL-Final | 11/18/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 11/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | AMIR NAZARIAN |
| Final | 11/26/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 11/26/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Final | 11/26/2024 | Approved | AMIR NAZARIAN |
| Final | 12/5/2024 | Corrections Issued | JOSE MACIAS |
| Final | 12/12/2024 | No Access for Inspection | AMIR NAZARIAN |
| Green Building Final | 12/12/2024 | No Access for Inspection | AMIR NAZARIAN |
| Final | 12/16/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Green Building Final | 12/16/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Final | 12/16/2024 | Approved | AMIR NAZARIAN |