1912 1/2 N CANYON DR 90068
Certificate Information: 1912 1/2 N CANYON DR 90068
- Application / Permit
- 23014-10000-00338
- Plan Check / Job No.
- B22LA26920
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED (35'-2" x 32'-2") IRREGULAR SHAPED ADDITION TO AND CONVERT (130 S.F) PORTION OF EX. DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT WITH AN ATTACHED PORCH PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 9/25/2023
- Issuing Office
- Current Status
- CofO Issued on 5/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | ROSENDO MEDINA |
| Corrections Issued | 2/14/2023 | ROSENDO MEDINA |
| Plan Check Approved | 9/13/2023 | SARKIS HARABEDIAN |
| Issued | 9/25/2023 | APPLICANT |
| CofO in Progress | 5/12/2025 | CRAIG VAUGHAN |
| Permit Finaled | 5/17/2025 | DEROLD HAUFF |
| CofO Issued | 5/17/2025 | DEROLD HAUFF |
| Permit Finaled | 5/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/21/2023 | KIRK LINKLATER |
| Address approval | Cleared | 4/4/2023 | ADRIAN SANCHEZ |
| HPOZ | Cleared | 6/21/2023 | MICAELA TORRES-GIL |
| Low Impact Development (LID) | Cleared | 8/17/2023 | ANTHONY VARGAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2023 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/18/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/18/2023 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 9/8/2023 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/3/2024 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 1/4/2024 | No Access for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/10/2024 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 3/7/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 3/7/2024 | Approved | ROY SPAULDING |
| MERV13>=Rough | 3/7/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 3/7/2024 | Partial Approval | ROY SPAULDING |
| Insulation | 4/1/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 4/1/2024 | Approved | ROY SPAULDING |
| Shower Pan | 4/1/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 4/9/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 9/30/2024 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 9/30/2024 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 10/2/2024 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 10/8/2024 | Approved | CRAIG VAUGHAN |
| Final | 11/5/2024 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/5/2024 | Approved | CRAIG VAUGHAN |
| MERV13>=Final | 11/5/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/5/2024 | Approved | CRAIG VAUGHAN |
| Final | 11/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| Final | 5/9/2025 | OK to Issue CofO | CRAIG VAUGHAN |