3731 W VALLEYBRINK ROAD 90039

Certificate Information: 3731 W VALLEYBRINK ROAD 90039

Application / Permit
23014-10000-00335
Plan Check / Job No.
B23LA01212
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to accessory dwelling unit plus addition to accessory dwelling unit per LAMC 12.22 A.33 (c)-(d). All work done per engineering.
Permit Issued
Issued on 4/25/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2023 APPLICANT
Assigned to Plan Check Engineer 1/30/2023 MINA HABILI
Corrections Issued 1/30/2023 MINA HABILI
Building Plans Picked Up 2/1/2023 APPLICANT
Plan Check Approved 4/25/2023 DANIEL SMILEY
Issued 4/25/2023 APPLICANT
CofO in Progress 2/20/2024 HAMIK HARTOUNIAN
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/26/2023 ADRIAN SANCHEZ
Miscellaneous Cleared 4/5/2023 JASON CHAN
ZI Cleared 4/5/2023 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 4/20/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 4/20/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 4/20/2023 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/13/2023 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/26/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/10/2023 Partial Approval CRAIG VAUGHAN
Pre-Inspection 9/6/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Inspection JOSEPH MCGARRY
Green Building Rough 9/29/2023 Not Ready for Inspection JOSEPH MCGARRY
MERV13>=Rough 9/29/2023 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 10/5/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/5/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/11/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 10/11/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/11/2023 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 10/11/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/18/2023 Approved JOSEPH MCGARRY
Insulation 10/18/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 10/18/2023 Partial Approval JOSEPH MCGARRY
Drywall Nailing 10/24/2023 Approved JOSH MEISTER
PLUMBING-Rough 12/7/2023 Conditional Approval HAMIK HARTOUNIAN
Sewer 12/7/2023 Approved HAMIK HARTOUNIAN
Final 1/11/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/11/2024 Approved HAMIK HARTOUNIAN
Green Building Final 1/11/2024 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 1/11/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/11/2024 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 1/11/2024 Approved HAMIK HARTOUNIAN
Final 1/30/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 1/30/2024 Approved HAMIK HARTOUNIAN
Final 2/8/2024 OK to Issue CofO HAMIK HARTOUNIAN