5301 N HAZELTINE AVE 91401
Certificate Information: 5301 N HAZELTINE AVE 91401
- Application / Permit
- 23014-10000-00329
- Plan Check / Job No.
- B23LA01176
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: 13'10" X 24'6" ADDITION TO REAR OF (E) SFD PER WFPP
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- Issued on 6/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2023 | JOHNPAUL ISIP |
| Corrections Issued | 2/6/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 2/10/2023 | EDWIN ESPIN |
| Plan Check Approved | 2/14/2023 | OMAR GARNICA |
| No Progress | 6/2/2023 | OMAR GARNICA |
| Plan Check Approved | 6/2/2023 | OMAR GARNICA |
| Plan Check Approved | 6/5/2023 | OMAR GARNICA |
| Issued | 6/5/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/9/2023 | RYAN KIM |
| Sewer availability | Cleared | 2/9/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | ROSE MARIE SMITH |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: C36271 | 26030 SANDBURG PL STEVENSON RANCH, CA 91381 |
| Contractor | Lindsey Paul G; Lic. No.: 441327-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/23/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/28/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 6/28/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 8/8/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/10/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/10/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/10/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/10/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/28/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/28/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 8/28/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/8/2023 | Approved | RYAN SALAZAR |
| Final | 10/6/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/6/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 10/6/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 10/6/2023 | Approved | RYAN SALAZAR |