1651 W 84TH PL 90047
Certificate Information: 1651 W 84TH PL 90047
- Application / Permit
- 23014-10000-00328
- Plan Check / Job No.
- B23LA01166
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan - PROPOSED CONVERSION OF EXISTING GARAGE TO ADU AND 2STROY ADDITION FOR ADU PER LAMC 12.22 A33(c)AND (d)
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | DANIEL SANJUAN |
| Corrections Issued | 2/9/2023 | DANIEL SANJUAN |
| Plan Check Approved | 6/29/2023 | FARSHAD ALIMOHAMADI |
| Issued | 7/20/2023 | APPLICANT |
| CofO in Progress | 1/14/2025 | SABAS ALONSO |
| CofO Issued | 1/15/2025 | DEROLD HAUFF |
| Permit Finaled | 1/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/14/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/15/2023 | JEANIE LAM |
| Construction within easement | Cleared | 4/29/2023 | RIDWAN HARDY |
| Construction near power lines | Cleared | 6/3/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Banning,, George Kwame; Lic. No.: NA53074 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/21/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 8/22/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/22/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/31/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/24/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/24/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/24/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/24/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 10/31/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/31/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/13/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/20/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/30/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/30/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/30/2024 | Approved | ENRIQUE MIRELES |
| Final | 2/20/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Drilled-In Anchors | 4/17/2024 | Approved | JOSE MACIAS |
| Final | 12/26/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 1/13/2025 | OK to Issue CofO | SABAS ALONSO |