4649 E SAN ANDREAS AVE 90065

Certificate Information: 4649 E SAN ANDREAS AVE 90065

Application / Permit
23014-10000-00319
Plan Check / Job No.
B23LA01124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) 2-STORY SFD AND ADDITION OF 62 SF.
Permit Issued
Issued on 8/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 VIVIAN LAO
Corrections Issued 2/19/2023 ERIC WONG
Quality Review Completed 2/23/2023 PETER KIM
Building Plans Picked Up 2/27/2023 APPLICANT
Applicant returned to address corrections 6/27/2023 VIVIAN LAO
Plan Check Approved 7/10/2023 VIVIAN LAO
Issued 8/17/2023 APPLICANT
CofO in Progress 12/3/2024 ALIZAH MAYAGOITIA
Permit Finaled 12/12/2024 DEROLD HAUFF
CofO Issued 12/12/2024 DEROLD HAUFF
Permit Finaled 12/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/14/2023 STEVE MELGAR
ZI Cleared 5/9/2023 PABLO ESTRADA
Specific Plan Cleared 5/16/2023 PABLO ESTRADA

Contact Information

Contractor Landmark Building & Design Inc; Lic. No.: 982610-B 4717 VAN NUYS BLVD STE 104      SHERMAN OAKS, CA 91403
Engineer Charifa,, Rizaldy Dizon; Lic. No.: C62585 1930 W. GLENOAKS BLVD.,   SUITE 12    GLENDALE, CA 91201

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/7/2023 Corrections Issued OSVALDO PARAMO
Deputy Drilled-In Anchors 9/19/2023 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/21/2023 Corrections Issued OSVALDO PARAMO
Deputy Drilled-In Anchors 10/3/2023 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 10/4/2023 Partial Approval OSVALDO PARAMO
Green Building Rough 10/4/2023 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 12/22/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 12/22/2023 Corrections Issued OSVALDO PARAMO
Green Building Rough 12/22/2023 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 12/22/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 12/22/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 1/10/2024 Corrections Issued OSVALDO PARAMO
HVAC-Rough 1/10/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 1/10/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 1/16/2024 Partial Inspection OSVALDO PARAMO
HVAC-Rough 1/16/2024 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 1/16/2024 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 1/17/2024 Corrections Issued OSVALDO PARAMO
Green Building Rough 1/17/2024 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 1/30/2024 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 1/30/2024 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 2/9/2024 Conditional Approval OSVALDO PARAMO
Green Building Rough 2/9/2024 Approved OSVALDO PARAMO
Special/Order Compliance 2/16/2024 Corrections Issued SCOTT FINNILA
Insulation 2/20/2024 Conditional Approval OSVALDO PARAMO
Drywall Nailing 3/4/2024 Approved OSVALDO PARAMO
Shower Pan 3/26/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/11/2024 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 5/7/2024 Partial Approval ALIZAH MAYAGOITIA
Final 7/31/2024 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 7/31/2024 Approved OSVALDO PARAMO
Green Building Final 7/31/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 7/31/2024 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 7/31/2024 Not Ready for Inspection OSVALDO PARAMO
Final 9/20/2024 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/21/2024 Approved ROY SPAULDING
Final 10/21/2024 Corrections Issued ROY SPAULDING
Green Building Final 10/21/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 10/21/2024 Approved ROY SPAULDING
Final 11/8/2024 Partial Approval ALIZAH MAYAGOITIA
Final 12/2/2024 OK to Issue CofO ALIZAH MAYAGOITIA