4649 E SAN ANDREAS AVE 90065
Certificate Information: 4649 E SAN ANDREAS AVE 90065
- Application / Permit
- 23014-10000-00319
- Plan Check / Job No.
- B23LA01124
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF (E) 2-STORY SFD AND ADDITION OF 62 SF.
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | VIVIAN LAO |
| Corrections Issued | 2/19/2023 | ERIC WONG |
| Quality Review Completed | 2/23/2023 | PETER KIM |
| Building Plans Picked Up | 2/27/2023 | APPLICANT |
| Applicant returned to address corrections | 6/27/2023 | VIVIAN LAO |
| Plan Check Approved | 7/10/2023 | VIVIAN LAO |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 12/3/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
| CofO Issued | 12/12/2024 | DEROLD HAUFF |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/10/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | STEVE MELGAR |
| ZI | Cleared | 5/9/2023 | PABLO ESTRADA |
| Specific Plan | Cleared | 5/16/2023 | PABLO ESTRADA |
Contact Information
| Contractor | Landmark Building & Design Inc; Lic. No.: 982610-B | 4717 VAN NUYS BLVD STE 104 SHERMAN OAKS, CA 91403 |
| Engineer | Charifa,, Rizaldy Dizon; Lic. No.: C62585 | 1930 W. GLENOAKS BLVD., SUITE 12 GLENDALE, CA 91201 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/7/2023 | Corrections Issued | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 9/19/2023 | Conditional Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Corrections Issued | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 10/3/2023 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/4/2023 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/22/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/22/2023 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 12/22/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 12/22/2023 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 12/22/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 1/10/2024 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 1/10/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 1/10/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 1/16/2024 | Partial Inspection | OSVALDO PARAMO |
| HVAC-Rough | 1/16/2024 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 1/16/2024 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/17/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 1/17/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/30/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/9/2024 | Conditional Approval | OSVALDO PARAMO |
| Green Building Rough | 2/9/2024 | Approved | OSVALDO PARAMO |
| Special/Order Compliance | 2/16/2024 | Corrections Issued | SCOTT FINNILA |
| Insulation | 2/20/2024 | Conditional Approval | OSVALDO PARAMO |
| Drywall Nailing | 3/4/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 3/26/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/7/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 7/31/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/31/2024 | Approved | OSVALDO PARAMO |
| Green Building Final | 7/31/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 7/31/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 7/31/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 9/20/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | ROY SPAULDING |
| Final | 10/21/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 10/21/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 10/21/2024 | Approved | ROY SPAULDING |
| Final | 11/8/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 12/2/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |