839 W 104TH PL 90044

Certificate Information: 839 W 104TH PL 90044

Application / Permit
23014-10000-00255
Plan Check / Job No.
B23LA00898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan; 253 SF Addition & Remodel To Ex. 1-Sty SFD
Permit Issued
Issued on 6/2/2023
Issuing Office
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2023 APPLICANT
Assigned to Plan Check Engineer 1/31/2023 MOHAMMAD ESMAILI
Corrections Issued 1/31/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 4/17/2023 MOHAMMAD ESMAILI
Plan Check Approved 5/11/2023 MOHAMMAD ESMAILI
Issued 6/2/2023 APPLICANT
CofO in Progress 10/15/2025 BEN MOLSTAD
Permit Finaled 10/17/2025 ANSON MAGLASANG
CofO Issued 10/17/2025 ANSON MAGLASANG
Permit Finaled 10/17/2025 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/30/2023 TREVOR QUAN
Sewer availability Cleared 3/30/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/3/2023 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251
Engineer Hamilton,, John O; Lic. No.: NA53284       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 10/17/2024 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 10/21/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 11/15/2024 Partial Approval BEN MOLSTAD
PLUMBING-Rough 11/15/2024 Partial Approval BEN MOLSTAD
Insulation 11/19/2024 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 12/4/2024 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued BEN MOLSTAD
Green Building Rough 12/4/2024 Not Ready for Inspection BEN MOLSTAD
Deputy Wood Construction 12/5/2024 Conditional Approval BEN MOLSTAD
BUILDING-Rough-Frame 5/30/2025 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 5/30/2025 Corrections Issued BEN MOLSTAD
Green Building Rough 5/30/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 5/30/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 6/2/2025 Not Ready for Inspection BEN MOLSTAD
Wood Frame 6/2/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 6/4/2025 Not Ready for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Partial Approval BEN MOLSTAD
Green Building Rough 6/4/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 7/11/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 7/11/2025 Partial Approval BEN MOLSTAD
PLUMBING-Rough 7/11/2025 Partial Approval BEN MOLSTAD
Insulation 7/15/2025 Approved BEN MOLSTAD
Drywall Nailing 7/25/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 8/12/2025 Corrections Issued BEN MOLSTAD
Interior/Exterior Lathing 8/14/2025 Approved BEN MOLSTAD
PLUMBING-Rough 9/24/2025 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 10/10/2025 Approved BEN MOLSTAD
Final 10/10/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 10/10/2025 Approved BEN MOLSTAD
Green Building Final 10/10/2025 Approved BEN MOLSTAD
Green Building Rough 10/10/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Approved BEN MOLSTAD
Smoke Detectors 10/10/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 10/15/2025 Approved BEN MOLSTAD
Final 10/15/2025 OK to Issue CofO BEN MOLSTAD
HVAC-Final 10/15/2025 Approved BEN MOLSTAD
PLUMBING-Final 10/15/2025 Approved BEN MOLSTAD
Service/Power Release 10/15/2025 Approved BEN MOLSTAD