1032 E VERNON AVE 90291
Certificate Information: 1032 E VERNON AVE 90291
- Application / Permit
- 23014-10000-00231
- Plan Check / Job No.
- B23LA00794
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage into ADU per LAMC 12.22 A.33 0(c)-(d) with addition to converted ADU
- Permit Issued
- Issued on 5/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | VICTOR CHEN |
| Corrections Issued | 1/30/2023 | VICTOR CHEN |
| Building Plans Picked Up | 2/1/2023 | APPLICANT |
| Applicant returned to address corrections | 3/3/2023 | LUKE GONZALES |
| Plan Check Approved | 3/10/2023 | RAHEL BEYENE |
| Issued | 5/1/2023 | APPLICANT |
| CofO in Progress | 11/29/2023 | HERBERT GIRON |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
| CofO Issued | 11/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 2/16/2023 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 2/21/2023 | EDUARDO HERMOSO |
| Construction near power lines | Cleared | 2/23/2023 | OSCAR CASTRO |
Contact Information
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Klein Construction; Lic. No.: 891079-B | 13858 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/22/2023 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/24/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 5/26/2023 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 6/1/2023 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 6/1/2023 | Approved | EVAN COOPER |
| Sewer | 6/9/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/13/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/26/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/6/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 7/18/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 7/18/2023 | Corrections Issued | EVAN COOPER |
| Insulation | 7/18/2023 | Corrections Issued | EVAN COOPER |
| Shower Pan | 7/18/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 7/24/2023 | Corrections Issued | EVAN COOPER |
| Insulation | 8/1/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 8/8/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | JESUS RODRIGUEZ |
| Final | 10/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 10/30/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/30/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Required | JESUS RODRIGUEZ |
| Smoke Detectors | 10/30/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/14/2023 | Approved | HERBERT GIRON |
| Final | 11/14/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/14/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/14/2023 | Approved | HERBERT GIRON |
| Final | 11/28/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 11/28/2023 | Approved | HERBERT GIRON |