1032 E VERNON AVE 90291

Certificate Information: 1032 E VERNON AVE 90291

Application / Permit
23014-10000-00231
Plan Check / Job No.
B23LA00794
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage into ADU per LAMC 12.22 A.33 0(c)-(d) with addition to converted ADU
Permit Issued
Issued on 5/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2023 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 VICTOR CHEN
Corrections Issued 1/30/2023 VICTOR CHEN
Building Plans Picked Up 2/1/2023 APPLICANT
Applicant returned to address corrections 3/3/2023 LUKE GONZALES
Plan Check Approved 3/10/2023 RAHEL BEYENE
Issued 5/1/2023 APPLICANT
CofO in Progress 11/29/2023 HERBERT GIRON
Permit Finaled 11/29/2023 DANIEL ORRANTE
CofO Issued 11/29/2023 DANIEL ORRANTE
Permit Finaled 11/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/14/2023 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 2/16/2023 AHMED AMARRAGY
Sewer availability Cleared 2/16/2023 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 2/21/2023 AHMED AMARRAGY
Specific Plan Cleared 2/21/2023 EDUARDO HERMOSO
Construction near power lines Cleared 2/23/2023 OSCAR CASTRO

Contact Information

Architect Thibodeau,, Robert E; Lic. No.: C25585 812 LINCOLN BLVD      VENICE, CA 90291
Contractor Klein Construction; Lic. No.: 891079-B 13858 CHANDLER BLVD      SHERMAN OAKS, CA 91401
Engineer Nohroodi,, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 5/24/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 5/26/2023 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 6/1/2023 Approved EVAN COOPER
Footing/Foundation/Slab 6/1/2023 Approved EVAN COOPER
Sewer 6/9/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Approved JESUS RODRIGUEZ
Underground Mechanical 6/13/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 6/26/2023 Approved EVAN COOPER
Interior/Exterior Lathing 7/6/2023 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/18/2023 Approved EVAN COOPER
HVAC-Rough 7/18/2023 Corrections Issued EVAN COOPER
Insulation 7/18/2023 Corrections Issued EVAN COOPER
Shower Pan 7/18/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Approved EVAN COOPER
HVAC-Rough 7/24/2023 Corrections Issued EVAN COOPER
Insulation 8/1/2023 Approved EVAN COOPER
Drywall Nailing 8/8/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/30/2023 Approved JESUS RODRIGUEZ
Final 10/30/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/30/2023 Approved JESUS RODRIGUEZ
Green Building Rough 10/30/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Not Required JESUS RODRIGUEZ
Smoke Detectors 10/30/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/14/2023 Approved HERBERT GIRON
Final 11/14/2023 Corrections Issued HERBERT GIRON
HVAC-Final 11/14/2023 Approved HERBERT GIRON
PLUMBING-Final 11/14/2023 Approved HERBERT GIRON
Final 11/28/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 11/28/2023 Approved HERBERT GIRON